First Fix Plumbing: Pipes and Connections
What first fix plumbing covers, what it costs, and the communication failures that turn a simple job into a paperwork nightmare.
Your plumber won't be in the loft for long at first fix. The pipework is the easy bit. What's hard is making sure the right pipes end up in the right walls and joist bays, that nobody skips the pressure test before the floor is boarded, and that the ensuite waste really does fall to the soil stack.
First fix plumbing covers everything that gets buried: hot and cold supplies to the ensuite and any basin, waste pipes to the stack, and flow and return pipes to the new radiators. The joists in a loft floor are designed by the structural engineer, so any notch or hole for a pipe has to stay within the limits that design allows.
What this guide covers
- 01What gets installed
- 02Push-fit vs copper
- 03Wall chases and structural limits
- 04What it costs
- 05What to check before walls close
- 06The Gas Safe certificate problem
- 07Coordinating with other trades
- 08Cold water and insulation requirements
Premium content: included with an Access Pass
This guide is part of the buildwiz.uk Access Pass. Get full access to every project guide, planning through to completion.
Get Access Pass£49, paid once. 24 months access.
Already bought the Access Pass? Sign in
General guidance for homeowners in England (and Wales where we say so), not professional advice. Every site is different: check anything that affects your build with a qualified professional, your local council or building control. Terms
Frequently asked questions
Reference guides for this task
Free guides to the tools, materials and terms this step involves.
Tools
Materials
- Compression Fittings
- Copper Pipe 15mm
- Copper Pipe 22mm
- Lintel
- Pipe Lagging
- Plasterboard Standard (12.5mm)
- Push-Fit Fittings
- Push-Fit Pipe 15mm (Speedfit)
- Push-Fit Pipe 22mm (Speedfit)
- Radiator
- Soil Pipe 110mm
- Solvent-weld fittings
- Solvent-Weld Waste Pipe (32mm/40mm)
- Stop Valves
- Twin-and-Earth Cable 1.5mm²
- Underfloor heating manifold