Part C
Approved Document C: Site Preparation and Resistance to Contaminants and Moisture
Site preparation and resistance to contaminants and moisture
Also known as
Part CApproved Document CAD CSite Preparation
What Part C requires for a home project
The Part C requirements and terms the buildwiz guides rely on, with paragraph references where the document gives one. Check the current edition on gov.uk before you build to it.
Limits and figures
- DPM good-practice lap
- Recommended lap dimension where DPM sheets join under a floor slab. Approved Document C 4.8 asks for sealed joints but sets no lap width; 150mm (gr8:guidance/dpm-joint-overlap-minimum) is the least to accept. NHBC Standards Chapter 5.1 and BRE Good Building Guide 5 recommend 300mm laps for routine domestic work because real-site placement, foot traffic, and tape adhesion are imperfect; a 300mm lap absorbs slippage and keeps the seal intact under the slab pour.
- DPM minimum gauge for radon-affected areas
- Minimum radon barrier for any radon protection: basic protection (radon potential 3-10% on the UK Health Security Agency map) and full protection (above 10%) both need a radon-resistant membrane of at least 400 micron (1600 gauge) polyethylene, or a certified proprietary radon barrier, across the whole footprint and bridging the cavity via a cavity tray, with every lap, joint and service penetration sealed airtight (not just waterproof). BRE BR 211:2023 section 6.2.1 advises a membrane of 400 microns or above, because thinner polyethylene is unlikely to withstand construction damage, and Approved Document C paras 2.39-2.40 point to BR 211. A 1200 gauge (300 micron) DPM is a damp-proof membrane, not a radon barrier. Certified radon barriers come in 400 micron and heavier grades. The barrier doubles as the floor's moisture barrier. Full protection adds a radon sump that can be fitted with a fan (solid floor) or a ventilated sub-floor void (suspended floor). Below 3% radon potential, no radon protection is needed.
- Treated timber: zone near DPC level (trade practice)
- Common UK practice treats structural softwood built into or bearing on masonry close to DPC level (wall plates on blockwork, joist ends, fillets in concrete floors) as needing preservative treatment or a naturally durable species. Approved Document C does not set this as a timber rule: its 150mm figure is the minimum height of the DPC above the adjoining ground (paragraph 5.5). Take the treatment requirement from BS 8417 and the engineer's specification.
- Untreated softwood damp-environment decay onset
- Onset window for visible rot when untreated softwood sits in damp conditions such as direct contact with masonry, ground or persistent condensation in a roof void. The range covers typical UK species and exposure levels. Used when weighing the small treatment premium against the cost of rebuilding a wall plate or roof that has failed: Approved Document C addresses separation from ground moisture in paragraph 4.13 and treatment of timber fillets laid in concrete in paragraph 4.11. It does not establish a general treatment rule for structural timber within 150mm of a DPC; specify treatment for the exposure and construction detail.
Terms explained
- BR 211
- BRE guidance document specifying when and how radon protective measures are required in new buildings and extensions. Current edition is BR 211:2023 (6th edition, May 2023), which supersedes and withdraws BR 211:2015. Cited in Approved Document C as the technical route for compliance. Covers both basic protection (membrane) and full protection (membrane + sump) tiers. Section 6.2.1 advises a radon membrane of 400 microns (1600 gauge) or above.
- Breathable Roof Membrane
- Modern breathable underlay laid over rafters beneath the battens and tiles. Allows water vapour to escape from the roof space while preventing wind-driven rain from entering. Has largely replaced traditional bitumen roofing felt in new construction. Required by current Building Regulations.
- Butyl Sealing Tape
- A self-adhesive double-sided or single-sided tape with a butyl rubber adhesive layer, used to join overlapping sheets of damp-proof membrane (DPM) and to seal membrane to wall, column, or service penetrations. The adhesive flows to conform to surface irregularities, creating a continuous watertight bond. Required at all DPM joints and upstands before concrete oversite or screed is poured. Available in 50mm and 100mm widths.
- Cavity board
- A strip of timber, foam, or polystyrene dragged up through the cavity as brickwork courses are laid, catching mortar droppings that would otherwise land on the DPC or wall ties and bridge the cavity. Removed and cleaned at intervals during bricklaying.
- Cavity closer
- Prefabricated insulated frames installed at window and door openings to close the cavity and prevent thermal bridging. They help meet Parts C (moisture) and L (thermal) of the Building Regulations; the 0.45 m²K/W minimum thermal resistance comes from the Accredited Construction Details, not Part L itself, and in a masonry house wall Approved Document B (Diagram 5.3) asks only that the cavity is closed around openings, with no fire rating for the closer. First-fix installation during wall construction is required by NHBC/LABC standards.
- Cavity tray
- Preformed angles and straights made from pitch-polymer or CPT, installed at abutments where the extension roof meets the existing house wall to direct cavity moisture back outside through weep vents.
- Chipboard (P5 Moisture Resistant)
- T&G moisture-resistant chipboard for domestic floor decking. Cheaper than plywood with a smoother surface than OSB. P5 grade is load-bearing and moisture-resistant. Standard sheet 2400x600mm (T&G) or 2440x1220mm (square edge).
- Damp Proof Membrane (1200 Gauge)
- Heavy-duty polythene sheet (1200 gauge / 300 micron) laid under and within concrete floor slabs to prevent moisture rising from the ground. Joints must be overlapped by at least 150mm and taped. Building control will check this is present.
- DPM jointing tape
- Self-adhesive tape used to seal the overlapping joints in DPM sheets so the moisture barrier is continuous. Joints must be lapped by at least 150mm and taped; untaped joints are a building control failure point.
- Dry Ridge System
- Mechanical fixing system for ridge tiles that eliminates the need for mortar bedding. Includes a roll of ventilated membrane, clips and screws. Now required by Building Regulations on new builds and extensions for better ventilation and durability.
- Loft Leg
- Plastic or metal stilts enabling loft storage boards to sit above mineral wool insulation without compressing it. Standard solution to the compression problem in lofts.
- PIR Insulation Board 50mm
- 50mm polyisocyanurate rigid insulation board with foil facing. High thermal performance for its thickness. Used in walls, roofs and floors. Common brands include Celotex and Kingspan. Standard board size 2400x1200mm.
- PIR Insulation Board 75mm
- 75mm polyisocyanurate rigid insulation board. Often used in combination with other thicknesses to achieve the required U-value specified by building control.
- Plasterboard Moisture Resistant (Green Board)
- Moisture-resistant plasterboard with a green paper facing, designed for use in kitchens, bathrooms and other areas subject to intermittent moisture. Not waterproof but resists humidity better than standard plasterboard. Required behind tiles in wet areas.
- Polyethylene DPC Roll
- Polyethylene strip laid in the mortar bed to form the horizontal damp-proof course in new-build walls. Available in widths from 100mm to 600mm; width must match or exceed wall width.
- Proprietary vapour control membrane
- Purpose-made multi-layer vapour control membrane (e.g. DuPont Airguard Control, Pro Clima INTELLO) with targeted vapour resistance (sd 5-18m). Meets NHBC Standards 6.2.12 UKAS certification requirement, unlike cheap polythene sheeting.
- Radon
- A naturally occurring radioactive gas produced by the decay of uranium in certain rocks and soils. It is colourless and odourless, seeps from the ground into buildings, and accumulates indoors at ground level. A Part C contaminant, measured in becquerels per cubic metre (Bq/m³). The UK's second-leading cause of lung cancer after smoking.
- Radon Barrier Membrane (1600 Gauge)
- A radon-resistant gas barrier laid across the extension floor in radon-affected areas. BRE BR 211:2023 (section 6.2.1) advises at least 400 micron (1600 gauge) polyethylene, or a certified proprietary radon barrier, for both basic and full protection; look for a BBA certificate for the gas function and EN 13967 marking for the moisture function. Sealed airtight at all laps and service penetrations (not just lapped like a moisture DPM). Doubles as the moisture barrier, so it replaces the standard 1200-gauge DPM in affected areas. Sold in 4m x 20m / 80m² rolls.
- Radon sump
- A sealed void beneath the floor slab connected to a pipe that allows radon gas to be extracted. Forms part of full radon protection in higher-risk postcodes (above roughly 10% radon probability on the UK Health Security Agency map) per Approved Document C. Radon risk is property-specific, so check the postcode on the UKHSA map rather than relying on a fixed county list. Building control inspects for the sump during the oversite visit in affected areas.
- Ridge Tiles
- Shaped tiles that cap the apex of a pitched roof. Must match the roof tile material and colour. Traditionally bedded on mortar but increasingly installed with dry ridge systems for a maintenance-free finish.
- Threshold drainage
- Correct threshold drainage requires the patio to slope away from the house with a drainage channel at the threshold. Wrong sill fall direction is the most common cause of post-installation water ingress. Part C compliance requirement.
- Treated Timber (Tanalised)
- Timber pressure-treated with preservative (typically tanalith) to resist rot and insect attack. Essential for any timber in contact with or close to the ground, external use, or built into masonry near DPC level. Has a distinctive green tint when new.
- Underfelt collar
- Manufacturer-specific junction membrane that bridges between the breathable roof membrane and the roof window frame. Must be the correct type for the window product (Velux and Fakro collars are not interchangeable). Breathable membrane must be dressed beneath the collar, not on top, turned up 75mm against a fixing batten per DuPont Tyvek technical manual.
- Ventilated Soffit Board
- The board that closes the underside of the roof overhang between the fascia and the wall face. The ventilated version has slots or a continuous strip giving the eaves airflow that Building Regulations require for a cold roof void (commonly a 10mm or 25mm continuous gap). Supplied as flat 9mm uPVC sheet or as pre-vented hollow soffit.
- Weep vent
- Small plastic insert placed in the perpend (vertical mortar joint) below a cavity tray to allow water that has entered the cavity to drain back outside. Required at maximum 900mm centres per Approved Document C.
Pages where Part C comes up
14 guides reference Part C, grouped by build phase.
Planning
Groundwork
Want the full picture?
The buildwiz build guides walk through a UK extension in sequence and link to Part C (and every other Approved Document) at the exact stage it bites. That is usually a more productive way to use this material than reading the document cover to cover.