Single Storey Rear Extension

Project manage your single storey rear extension, phase by phase.

See the whole build laid out in order, from planning permission to sign-off. Browse every task free; the detailed guidance is included with the Access Pass.

8
Phases
71
Tasks
732
Subtasks

About this guide

The step-by-step guide to project managing a single storey rear extension in the UK, covering planning permission, builder selection, snagging, and sign-off for homeowners with no building experience.

Phase 01

12–18 wk · typical duration

Planning & Permissions.

Everything you need to sort before a single brick is laid

18 tasks

In this phase

162 subtasks

Step-by-step

0% · 0 / 162 subtasks

Your progress

The tasks

In recommended orderclick to open

Phase 05

4–8 wk · typical duration

Specification.

Choosing the finishes and fittings, and placing the orders that first fix and second fix depend on.

3 tasks

In this phase

35 subtasks

Step-by-step

0% · 0 / 35 subtasks

Your progress