Wakefield planning statistics

Householder applications decided in the year to June 2026, compared with the rest of England.

How long does planning permission take in Wakefield?

Wakefield decided 51.0% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Wakefield is highlighted on the map. See on the map

Within 8 weeks, no extension

51.0%

233rd of 297

11.7 points slower than England

Granted

94.6%

96th of 297

4.1 points higher than England

Extension of time

43.4%

234th of 297

11.1 points higher than England

Decisions (12 months)

553

Wakefield decided 553 householder applications in the year to June 2026, granting 94.6%.

51.0% were decided within 8 weeks with no extension, against 62.7% across England (233rd of 297 for speed).

A further 43.4% were decided under an extension of time agreed with the applicant.

Of 11 householder appeals decided in the same period, 54.5% were allowed.

How quickly decisions are made

Wakefield against England, share of householder decisions each quarter

  • Within 8 weeks, no extension
  • Extension of time
  • England, within 8 weeks
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterWithin 8 weeks, no extensionExtension of timeEngland, within 8 weeks
2008 Q187.6%0.0%89.5%
2008 Q286.5%0.0%89.4%
2008 Q388.1%0.0%89.7%
2008 Q486.2%0.0%90.3%
2009 Q190.6%0.0%90.3%
2009 Q292.6%0.0%91.7%
2009 Q391.5%0.0%91.4%
2009 Q487.9%0.0%91.0%
2010 Q191.9%0.0%88.8%
2010 Q287.7%0.0%89.8%
2010 Q387.6%0.0%88.4%
2010 Q487.1%0.0%87.7%
2011 Q188.4%0.0%86.4%
2011 Q286.4%0.0%85.9%
2011 Q385.8%0.0%84.9%
2011 Q486.5%0.0%84.9%
2012 Q191.7%0.0%83.7%
2012 Q288.9%0.0%84.2%
2012 Q385.4%0.0%82.9%
2012 Q481.8%0.0%85.2%
2013 Q193.7%0.0%85.7%
2013 Q288.7%0.0%86.3%
2013 Q393.5%0.0%85.3%
2013 Q486.3%0.0%86.3%
2014 Q189.5%0.0%85.4%
2014 Q270.1%8.8%84.9%
2014 Q381.2%9.6%82.5%
2014 Q478.4%11.4%82.1%
2015 Q178.2%0.0%80.4%
2015 Q283.2%12.8%80.6%
2015 Q376.6%16.7%79.2%
2015 Q485.9%10.8%80.0%
2016 Q178.7%15.5%78.3%
2016 Q282.4%13.8%79.8%
2016 Q383.8%14.6%77.7%
2016 Q476.8%21.6%78.0%
2017 Q172.7%26.1%77.3%
2017 Q268.3%27.6%78.5%
2017 Q374.9%18.9%76.1%
2017 Q489.9%8.0%77.1%
2018 Q172.8%20.4%73.7%
2018 Q264.7%29.8%74.0%
2018 Q370.7%23.6%72.7%
2018 Q473.1%24.2%72.7%
2019 Q161.5%35.8%69.9%
2019 Q275.4%20.8%72.1%
2019 Q371.3%26.7%69.6%
2019 Q472.9%25.9%71.5%
2020 Q161.1%36.6%68.4%
2020 Q229.7%66.9%63.9%
2020 Q312.6%82.4%63.8%
2020 Q417.3%76.7%65.3%
2021 Q119.1%63.0%59.4%
2021 Q225.8%54.4%58.4%
2021 Q335.9%57.0%53.1%
2021 Q442.2%50.8%53.0%
2022 Q140.8%51.2%51.6%
2022 Q245.3%48.2%56.0%
2022 Q341.4%53.7%53.3%
2022 Q444.0%47.3%54.1%
2023 Q140.2%56.1%53.5%
2023 Q232.1%61.8%58.5%
2023 Q342.1%54.2%59.0%
2023 Q448.9%44.3%59.8%
2024 Q151.5%43.2%58.8%
2024 Q243.7%49.0%64.4%
2024 Q351.5%42.6%64.2%
2024 Q454.3%40.2%65.6%
2025 Q148.2%48.9%62.1%
2025 Q252.0%44.4%65.0%
2025 Q360.5%38.2%62.5%
2025 Q460.8%35.0%64.7%
2026 Q135.5%47.6%60.6%
2026 Q246.5%51.6%62.7%

Share of applications granted

Wakefield against England

  • Wakefield
  • England
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterWakefieldEngland
2008 Q184.6%85.1%
2008 Q293.8%86.1%
2008 Q388.1%86.3%
2008 Q489.7%85.3%
2009 Q188.5%85.9%
2009 Q287.5%86.8%
2009 Q386.1%87.4%
2009 Q488.4%86.9%
2010 Q189.9%87.0%
2010 Q288.1%88.0%
2010 Q385.8%87.7%
2010 Q482.7%87.5%
2011 Q187.0%87.9%
2011 Q289.7%88.5%
2011 Q386.3%88.3%
2011 Q490.4%88.3%
2012 Q187.6%88.2%
2012 Q286.4%89.2%
2012 Q385.4%89.0%
2012 Q490.0%88.9%
2013 Q190.9%89.8%
2013 Q288.7%90.6%
2013 Q393.5%90.3%
2013 Q487.0%89.6%
2014 Q192.4%89.8%
2014 Q290.7%90.5%
2014 Q394.4%90.0%
2014 Q490.4%89.2%
2015 Q194.3%89.3%
2015 Q296.4%90.2%
2015 Q394.8%90.0%
2015 Q492.0%89.2%
2016 Q192.3%90.0%
2016 Q294.3%90.3%
2016 Q393.4%90.2%
2016 Q491.6%89.7%
2017 Q190.3%89.9%
2017 Q291.4%90.5%
2017 Q389.4%90.0%
2017 Q489.4%90.1%
2018 Q188.9%90.5%
2018 Q291.6%91.0%
2018 Q394.7%91.2%
2018 Q494.1%90.5%
2019 Q191.1%90.3%
2019 Q294.9%91.0%
2019 Q395.9%90.6%
2019 Q491.0%89.8%
2020 Q194.3%89.9%
2020 Q295.8%90.2%
2020 Q398.7%90.6%
2020 Q497.5%90.3%
2021 Q195.8%90.9%
2021 Q293.4%91.2%
2021 Q395.4%91.0%
2021 Q493.8%90.1%
2022 Q193.6%90.0%
2022 Q293.9%90.4%
2022 Q393.0%89.8%
2022 Q492.9%89.4%
2023 Q196.3%89.3%
2023 Q292.4%89.2%
2023 Q392.5%88.6%
2023 Q493.2%88.2%
2024 Q190.9%88.2%
2024 Q287.4%89.1%
2024 Q390.5%89.4%
2024 Q489.8%88.6%
2025 Q193.4%89.3%
2025 Q295.3%90.4%
2025 Q396.1%90.1%
2025 Q492.5%90.1%
2026 Q193.5%90.6%
2026 Q295.5%91.0%

How long decisions took

Householder decisions over the last 12 months

  • Within 8 weeks51.0%
  • 8 to 13 weeks4.5%
  • 13 to 26 weeks0.9%
  • Over 26 weeks0.2%
  • Extension of time agreed43.4%
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
Time takenDecisions
Within 8 weeks282
8 to 13 weeks25
13 to 26 weeks5
Over 26 weeks1
Extension of time agreed240

Appeals

Decided
11
Allowed
54.5%
Median wait
8 weeks

Householder appeals to the Planning Inspectorate decided in the same 12 months. England: 34.4% allowed.

Refusals overturned at appeal

10.3% of refusals were later overturned at appeal (July 2021 to June 2026): 25 appeals allowed against 242 refusals.

88th highest of 299 planning authorities. England: 8.9% (July 2021 to June 2026).

Householder refusals from MHCLG table PS2; appeals allowed from the Planning Inspectorate. Approximate: appeals decided in the period, which can relate to earlier refusals.

Larger home extensions (prior approval)

Single-storey rear extensions deeper than 4 metres on a detached house (3 metres otherwise), up to 8 metres (6 metres), can use prior approval instead of a planning application, except in conservation areas, National Landscapes and other protected areas.

Of 57 larger extension notifications between July 2025 and June 2026, 48 needed no approval, 6 were approved and 3 were refused.

Fewer than 10 decided in the period.

Figures as first published (provisional).

MHCLG live table PDR 1.

Enforcement

36 planning enforcement notices issued in the year to June 2026.

0.22 per 1,000 homes, against 0.17 across England. 58th highest of 294 planning authorities.

Covers all types of development, not only extensions.

MHCLG table P130; homes from the VOA Council Tax stock of properties.

Protected areas

11 conservation areas: Burton Park, Lower Westgate, Pontefract Castle, Pontefract Market Place, Sandal Castle, South Parade, St John's, The Mount, Upper Westgate, Wakefield Cathedral and Wentworth Terrace.

Wakefield has not published its Article 4 directions to the national planning data service, so the count may be incomplete.

Both can remove permitted development rights, so check with the council before relying on them. Permitted development rules

To check one postcode for a conservation area, listed buildings nearby, flood zone and radon, use the address check.

planning.data.gov.uk.

Builders

1,380 registered building and trade firms in 2026, 8.3 per 1,000 homes, about 0.4 householder decisions per firm a year.

79th lowest of 294 planning authorities. England median: 10.1 per 1,000 homes and 0.5 decisions per firm.

Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Finding a builder

ONS UK Business Counts; homes from the VOA Council Tax stock of properties; decisions from MHCLG table PS2.

Compared with neighbouring councils

Decisions and approvals in the year to June 2026; overturns over each council's appeal window; builders per 1,000 homes in 2026.

Decided within 8 weeks, no extension

Granted

Refusals overturned at appeal

Registered building firms per 1,000 homes

Questions about planning in Wakefield

How long does planning permission take in Wakefield?

Wakefield decided 51.0% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Is my house in a conservation area in Wakefield?

11 conservation areas: Burton Park, Lower Westgate, Pontefract Castle, Pontefract Market Place, Sandal Castle, South Parade, St John's, The Mount, Upper Westgate, Wakefield Cathedral and Wentworth Terrace. Most councils publish a conservation area map showing whether a street is inside one.

How many builders are there in Wakefield?

1,380 registered building and trade firms in 2026, 8.3 per 1,000 homes, about 0.4 householder decisions per firm a year. Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Do I need planning permission for an extension in Wakefield?

Many extensions can be built under permitted development without an application, but conservation areas and Article 4 directions can remove those rights, so check whether your address is in a conservation area or covered by an Article 4 direction before relying on them. Do you need planning permission?

Property prices and energy performance in Wakefield

Homes sold July 2023 to June 2026, matched to the floor area and energy rating on their Energy Performance Certificate.

Median price per m²

£2,436

12,987 sales

4% below Yorkshire and The Humber

Homes sold rated EPC A to C

51.0%

Median energy score 69

5.2 points above Yorkshire and The Humber

Value added by extending, per m²

£929

13.6% on the sale price

31% below Yorkshire and The Humber

Energy upgrade, no extension

+7.3%

Sale-price uplift when the energy score rose 5+ points

0.8 points above Yorkshire and The Humber

The median home sold in Wakefield was £200,000 for 83 m² of floor space. Price per m² is up 52% since 2015 (£1,638 to £2,491 per m², 2025). Across all 122,639 homes with a certificate, 50.0% are rated A to C on their latest one.

534 houses here were extended between two sales (second sale 2016 to 2026), adding a median 27 m². They sold for a median 13.6% more than similar unextended houses, £929 for each m² added. Will an extension pay for itself here?

Medians from HM Land Registry sale prices and MHCLG Energy Performance Certificates; groups under 30 sales or 50 extended houses are not shown. These describe past sales across many homes, not a valuation of any one. How these are worked out

Next steps for your extension

Compare every council · How we calculate these figures

Get new blog posts by email

One email each time we publish a new post on project managing your build. No spam. Unsubscribe anytime.