buildwiz.uk
East of England

Uttlesford planning statistics

Householder applications decided in the year to June 2026, compared with the rest of England.

Within 8 weeks, no extension

78.6%

50th of 297

15.9 points faster than England

Granted

81.6%

273rd of 297

8.9 points lower than England

Extension of time

15.7%

35th of 297

16.6 points lower than England

Decisions (12 months)

490

Uttlesford decided 490 householder applications in the year to June 2026, granting 81.6%.

78.6% were decided within 8 weeks with no extension, against 62.7% across England (50th of 297 for speed).

A further 15.7% were decided under an extension of time agreed with the applicant.

That is up from 72.4% a year earlier.

Of 18 householder appeals decided in the same period, 27.8% were allowed.

How quickly decisions are made

Uttlesford against England, share of householder decisions each quarter

  • Within 8 weeks, no extension
  • Extension of time
  • England, within 8 weeks
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterWithin 8 weeks, no extensionExtension of timeEngland, within 8 weeks
2008 Q191.2%0.0%89.5%
2008 Q288.1%0.0%89.4%
2008 Q392.0%0.0%89.7%
2008 Q491.2%0.0%90.3%
2009 Q184.8%0.0%90.3%
2009 Q273.4%0.0%91.7%
2009 Q378.8%0.0%91.4%
2009 Q474.3%0.0%91.0%
2010 Q193.1%0.0%88.8%
2010 Q293.3%0.0%89.8%
2010 Q395.8%0.0%88.4%
2010 Q490.6%0.0%87.7%
2011 Q193.6%0.0%86.4%
2011 Q294.0%0.0%85.9%
2011 Q386.6%0.0%84.9%
2011 Q485.8%0.0%84.9%
2012 Q192.8%0.0%83.7%
2012 Q282.5%0.0%84.2%
2012 Q370.4%0.0%82.9%
2012 Q471.3%0.0%85.2%
2013 Q193.2%0.0%85.7%
2013 Q292.5%0.0%86.3%
2013 Q394.0%0.0%85.3%
2013 Q492.9%0.0%86.3%
2014 Q193.2%0.0%85.4%
2014 Q293.8%0.0%84.9%
2014 Q394.1%0.0%82.5%
2014 Q495.1%0.0%82.1%
2015 Q192.5%4.5%80.4%
2015 Q289.5%2.5%80.6%
2015 Q390.0%3.3%79.2%
2015 Q489.3%7.3%80.0%
2016 Q181.6%9.2%78.3%
2016 Q286.1%5.2%79.8%
2016 Q382.0%10.8%77.7%
2016 Q485.7%6.9%78.0%
2017 Q172.9%9.7%77.3%
2017 Q267.8%9.8%78.5%
2017 Q370.0%14.5%76.1%
2017 Q471.0%14.0%77.1%
2018 Q167.9%21.2%73.7%
2018 Q278.0%9.3%74.0%
2018 Q381.8%8.6%72.7%
2018 Q463.7%16.2%72.7%
2019 Q153.0%12.2%69.9%
2019 Q273.6%19.4%72.1%
2019 Q360.8%24.7%69.6%
2019 Q459.1%19.4%71.5%
2020 Q161.1%21.5%68.4%
2020 Q271.0%23.3%63.9%
2020 Q364.7%31.8%63.8%
2020 Q455.0%33.3%65.3%
2021 Q163.3%25.1%59.4%
2021 Q264.3%24.2%58.4%
2021 Q360.5%29.2%53.1%
2021 Q467.2%26.6%53.0%
2022 Q178.9%18.3%51.6%
2022 Q263.1%28.2%56.0%
2022 Q362.3%28.5%53.3%
2022 Q462.9%33.6%54.1%
2023 Q154.7%39.2%53.5%
2023 Q265.1%24.4%58.5%
2023 Q352.8%39.8%59.0%
2023 Q465.7%28.4%59.8%
2024 Q159.2%29.3%58.8%
2024 Q267.4%23.9%64.4%
2024 Q360.6%25.0%64.2%
2024 Q468.0%17.0%65.6%
2025 Q177.6%18.4%62.1%
2025 Q282.7%11.5%65.0%
2025 Q378.4%16.5%62.5%
2025 Q487.0%8.7%64.7%
2026 Q177.5%17.6%60.6%
2026 Q269.4%21.6%62.7%

Share of applications granted

Uttlesford against England

  • Uttlesford
  • England
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterUttlesfordEngland
2008 Q174.8%85.1%
2008 Q284.9%86.1%
2008 Q373.9%86.3%
2008 Q482.4%85.3%
2009 Q186.2%85.9%
2009 Q282.9%86.8%
2009 Q390.0%87.4%
2009 Q488.5%86.9%
2010 Q185.5%87.0%
2010 Q282.2%88.0%
2010 Q386.1%87.7%
2010 Q489.4%87.5%
2011 Q180.3%87.9%
2011 Q284.8%88.5%
2011 Q392.0%88.3%
2011 Q487.4%88.3%
2012 Q188.9%88.2%
2012 Q287.2%89.2%
2012 Q390.5%89.0%
2012 Q492.8%88.9%
2013 Q189.7%89.8%
2013 Q289.4%90.6%
2013 Q390.4%90.3%
2013 Q491.2%89.6%
2014 Q191.0%89.8%
2014 Q293.8%90.5%
2014 Q393.5%90.0%
2014 Q491.8%89.2%
2015 Q187.2%89.3%
2015 Q290.5%90.2%
2015 Q394.7%90.0%
2015 Q487.6%89.2%
2016 Q193.3%90.0%
2016 Q294.3%90.3%
2016 Q388.1%90.2%
2016 Q484.0%89.7%
2017 Q176.8%89.9%
2017 Q286.4%90.5%
2017 Q388.0%90.0%
2017 Q488.2%90.1%
2018 Q186.4%90.5%
2018 Q279.5%91.0%
2018 Q383.4%91.2%
2018 Q481.0%90.5%
2019 Q172.6%90.3%
2019 Q278.0%91.0%
2019 Q378.4%90.6%
2019 Q475.8%89.8%
2020 Q171.1%89.9%
2020 Q273.9%90.2%
2020 Q381.5%90.6%
2020 Q478.3%90.3%
2021 Q175.8%90.9%
2021 Q271.7%91.2%
2021 Q378.7%91.0%
2021 Q485.4%90.1%
2022 Q183.9%90.0%
2022 Q280.5%90.4%
2022 Q388.4%89.8%
2022 Q482.9%89.4%
2023 Q178.4%89.3%
2023 Q281.4%89.2%
2023 Q382.0%88.6%
2023 Q479.9%88.2%
2024 Q182.2%88.2%
2024 Q284.1%89.1%
2024 Q387.9%89.4%
2024 Q481.7%88.6%
2025 Q182.4%89.3%
2025 Q284.6%90.4%
2025 Q383.5%90.1%
2025 Q479.0%90.1%
2026 Q178.4%90.6%
2026 Q285.6%91.0%

How long decisions took

Householder decisions over the last 12 months

  • Within 8 weeks78.6%
  • 8 to 13 weeks4.3%
  • 13 to 26 weeks1.4%
  • Over 26 weeks0.0%
  • Extension of time agreed15.7%
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
Time takenDecisions
Within 8 weeks385
8 to 13 weeks21
13 to 26 weeks7
Over 26 weeks0
Extension of time agreed77

Appeals

Decided
18
Allowed
27.8%
Median wait
18 weeks

Householder appeals to the Planning Inspectorate decided in the same 12 months. England: 34.4% allowed.

Local constraints

  • Uttlesford has published 42 conservation areas.
  • Uttlesford has published 18 Article 4 areas.

Both can remove permitted development rights. Not every council has published its data yet, so check with the council before relying on permitted development.

Next steps for your extension

Compare every council · How we calculate these figures

Get notified when new sections land

We're publishing new guides as they're finished. Join the list to find out when yours is ready.