Norwich planning statistics

Householder applications decided in the year to June 2026, compared with the rest of England.

How long does planning permission take in Norwich?

Norwich decided 77.8% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Norwich is highlighted on the map. See on the map

Within 8 weeks, no extension

77.8%

52nd of 297

15.1 points faster than England

Granted

97.6%

19th of 297

7.1 points higher than England

Extension of time

16.8%

43rd of 297

15.5 points lower than England

Decisions (12 months)

167

Norwich decided 167 householder applications in the year to June 2026, granting 97.6%.

77.8% were decided within 8 weeks with no extension, against 62.7% across England (52nd of 297 for speed).

A further 16.8% were decided under an extension of time agreed with the applicant.

How quickly decisions are made

Norwich against England, share of householder decisions each quarter

  • Within 8 weeks, no extension
  • Extension of time
  • England, within 8 weeks
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterWithin 8 weeks, no extensionExtension of timeEngland, within 8 weeks
2008 Q141.8%0.0%89.5%
2008 Q277.1%0.0%89.4%
2008 Q384.8%0.0%89.7%
2008 Q486.2%0.0%90.3%
2009 Q188.9%0.0%90.3%
2009 Q298.2%0.0%91.7%
2009 Q394.9%0.0%91.4%
2009 Q493.5%0.0%91.0%
2010 Q190.6%0.0%88.8%
2010 Q296.1%0.0%89.8%
2010 Q398.5%0.0%88.4%
2010 Q492.3%0.0%87.7%
2011 Q185.7%0.0%86.4%
2011 Q287.0%0.0%85.9%
2011 Q386.1%0.0%84.9%
2011 Q496.9%0.0%84.9%
2012 Q186.8%0.0%83.7%
2012 Q291.5%0.0%84.2%
2012 Q381.4%0.0%82.9%
2012 Q490.2%0.0%85.2%
2013 Q193.4%0.0%85.7%
2013 Q293.8%0.0%86.3%
2013 Q382.1%0.0%85.3%
2013 Q498.0%0.0%86.3%
2014 Q193.0%0.0%85.4%
2014 Q293.2%3.4%84.9%
2014 Q397.0%1.5%82.5%
2014 Q483.3%11.1%82.1%
2015 Q184.1%12.7%80.4%
2015 Q288.5%7.7%80.6%
2015 Q382.4%13.2%79.2%
2015 Q481.7%13.3%80.0%
2016 Q184.2%12.3%78.3%
2016 Q278.8%18.8%79.8%
2016 Q369.6%24.6%77.7%
2016 Q470.1%17.9%78.0%
2017 Q171.1%23.7%77.3%
2017 Q273.6%22.0%78.5%
2017 Q381.1%16.8%76.1%
2017 Q483.7%14.3%77.1%
2018 Q189.7%10.3%73.7%
2018 Q293.2%6.8%74.0%
2018 Q378.7%16.0%72.7%
2018 Q481.3%16.0%72.7%
2019 Q178.9%19.7%69.9%
2019 Q279.5%15.4%72.1%
2019 Q373.8%17.5%69.6%
2019 Q480.0%16.9%71.5%
2020 Q180.8%19.2%68.4%
2020 Q281.8%16.7%63.9%
2020 Q375.0%20.3%63.8%
2020 Q481.4%16.3%65.3%
2021 Q183.8%16.2%59.4%
2021 Q275.9%17.0%58.4%
2021 Q386.7%10.2%53.1%
2021 Q482.7%13.5%53.0%
2022 Q175.0%23.4%51.6%
2022 Q284.2%11.8%56.0%
2022 Q372.4%25.9%53.3%
2022 Q474.3%24.3%54.1%
2023 Q162.7%37.3%53.5%
2023 Q274.5%23.5%58.5%
2023 Q378.8%19.2%59.0%
2023 Q482.3%14.5%59.8%
2024 Q172.2%13.0%58.8%
2024 Q284.7%8.5%64.4%
2024 Q375.9%16.7%64.2%
2024 Q489.4%6.4%65.6%
2025 Q174.1%20.4%62.1%
2025 Q274.6%15.9%65.0%
2025 Q381.6%10.5%62.5%
2025 Q470.5%22.7%64.7%
2026 Q178.6%16.7%60.6%
2026 Q281.4%16.3%62.7%

Share of applications granted

Norwich against England

  • Norwich
  • England
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterNorwichEngland
2008 Q182.1%85.1%
2008 Q293.2%86.1%
2008 Q379.7%86.3%
2008 Q484.6%85.3%
2009 Q186.7%85.9%
2009 Q292.9%86.8%
2009 Q379.7%87.4%
2009 Q495.7%86.9%
2010 Q190.6%87.0%
2010 Q294.1%88.0%
2010 Q395.5%87.7%
2010 Q490.4%87.5%
2011 Q192.9%87.9%
2011 Q287.0%88.5%
2011 Q390.3%88.3%
2011 Q486.2%88.3%
2012 Q192.1%88.2%
2012 Q294.9%89.2%
2012 Q392.9%89.0%
2012 Q497.6%88.9%
2013 Q196.7%89.8%
2013 Q296.9%90.6%
2013 Q396.4%90.3%
2013 Q498.0%89.6%
2014 Q195.3%89.8%
2014 Q296.6%90.5%
2014 Q397.0%90.0%
2014 Q492.6%89.2%
2015 Q193.7%89.3%
2015 Q296.2%90.2%
2015 Q395.6%90.0%
2015 Q498.3%89.2%
2016 Q1100.0%90.0%
2016 Q296.3%90.3%
2016 Q394.2%90.2%
2016 Q494.0%89.7%
2017 Q193.4%89.9%
2017 Q294.5%90.5%
2017 Q394.7%90.0%
2017 Q493.9%90.1%
2018 Q197.1%90.5%
2018 Q298.6%91.0%
2018 Q396.0%91.2%
2018 Q498.7%90.5%
2019 Q195.8%90.3%
2019 Q296.2%91.0%
2019 Q388.8%90.6%
2019 Q498.5%89.8%
2020 Q194.5%89.9%
2020 Q2100.0%90.2%
2020 Q393.8%90.6%
2020 Q493.0%90.3%
2021 Q193.2%90.9%
2021 Q297.3%91.2%
2021 Q3100.0%91.0%
2021 Q495.2%90.1%
2022 Q195.3%90.0%
2022 Q297.4%90.4%
2022 Q398.3%89.8%
2022 Q497.3%89.4%
2023 Q196.6%89.3%
2023 Q2100.0%89.2%
2023 Q398.1%88.6%
2023 Q496.8%88.2%
2024 Q194.4%88.2%
2024 Q293.2%89.1%
2024 Q394.4%89.4%
2024 Q497.9%88.6%
2025 Q198.1%89.3%
2025 Q296.8%90.4%
2025 Q394.7%90.1%
2025 Q497.7%90.1%
2026 Q1100.0%90.6%
2026 Q297.7%91.0%

How long decisions took

Householder decisions over the last 12 months

  • Within 8 weeks77.8%
  • 8 to 13 weeks4.2%
  • 13 to 26 weeks0.6%
  • Over 26 weeks0.6%
  • Extension of time agreed16.8%
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
Time takenDecisions
Within 8 weeks130
8 to 13 weeks7
13 to 26 weeks1
Over 26 weeks1
Extension of time agreed28

Appeals

Decided
1
Allowed
0.0%
Median wait
27 weeks

Householder appeals to the Planning Inspectorate decided in the same 12 months. England: 34.4% allowed.

Refusals overturned at appeal

2.8% of refusals were later overturned at appeal (July 2021 to June 2026): 1 appeal allowed against 36 refusals.

8th lowest of 299 planning authorities. England: 8.9% (July 2021 to June 2026).

Householder refusals from MHCLG table PS2; appeals allowed from the Planning Inspectorate. Approximate: appeals decided in the period, which can relate to earlier refusals.

Larger home extensions (prior approval)

Single-storey rear extensions deeper than 4 metres on a detached house (3 metres otherwise), up to 8 metres (6 metres), can use prior approval instead of a planning application, except in conservation areas, National Landscapes and other protected areas.

Of 9 larger extension notifications between July 2025 and June 2026, 6 needed no approval, 3 were approved and 0 were refused.

Fewer than 10 decided in the period.

Figures as first published (provisional).

MHCLG live table PDR 1.

Enforcement

8 planning enforcement notices issued in the year to June 2026.

0.12 per 1,000 homes, against 0.17 across England. 132nd highest of 294 planning authorities.

Covers all types of development, not only extensions.

MHCLG table P130; homes from the VOA Council Tax stock of properties.

Protected areas

17 conservation areas: Bowthorpe, Bracondale, City Centre, Earlham, Eaton, Heigham Grove, Hellesdon, Mile Cross, Newmarket Road, Old Lakenham, Sewell, St Matthews and 5 more.

Norwich has not published its Article 4 directions to the national planning data service, so the count may be incomplete.

Both can remove permitted development rights, so check with the council before relying on them. Permitted development rules

To check one postcode for a conservation area, listed buildings nearby, flood zone and radon, use the address check.

planning.data.gov.uk.

Builders

370 registered building and trade firms in 2026, 5.3 per 1,000 homes, about 0.5 householder decisions per firm a year.

10th lowest of 294 planning authorities. England median: 10.1 per 1,000 homes and 0.5 decisions per firm.

Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Finding a builder

ONS UK Business Counts; homes from the VOA Council Tax stock of properties; decisions from MHCLG table PS2.

Compared with neighbouring councils

Decisions and approvals in the year to June 2026; overturns over each council's appeal window; builders per 1,000 homes in 2026.

Decided within 8 weeks, no extension

Granted

Refusals overturned at appeal

Registered building firms per 1,000 homes

Questions about planning in Norwich

How long does planning permission take in Norwich?

Norwich decided 77.8% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Is my house in a conservation area in Norwich?

17 conservation areas: Bowthorpe, Bracondale, City Centre, Earlham, Eaton, Heigham Grove, Hellesdon, Mile Cross, Newmarket Road, Old Lakenham, Sewell, St Matthews and 5 more. Most councils publish a conservation area map showing whether a street is inside one.

How many builders are there in Norwich?

370 registered building and trade firms in 2026, 5.3 per 1,000 homes, about 0.5 householder decisions per firm a year. Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Do I need planning permission for an extension in Norwich?

Many extensions can be built under permitted development without an application, but conservation areas and Article 4 directions can remove those rights, so check whether your address is in a conservation area or covered by an Article 4 direction before relying on them. Do you need planning permission?

Property prices and energy performance in Norwich

Homes sold July 2023 to June 2026, matched to the floor area and energy rating on their Energy Performance Certificate.

Median price per m²

£3,116

5,133 sales

20% below East of England

Homes sold rated EPC A to C

47.6%

Median energy score 68

5.0 points below East of England

Value added by extending, per m²

£1,473

11.9% on the sale price

27% below East of England

Energy upgrade, no extension

+2.5%

Sale-price uplift when the energy score rose 5+ points

1.7 points below East of England

The median home sold in Norwich was £235,000 for 75 m² of floor space. Price per m² is up 37% since 2015 (£2,273 to £3,119 per m², 2025). Across all 53,802 homes with a certificate, 55.3% are rated A to C on their latest one.

143 houses here were extended between two sales (second sale 2016 to 2026), adding a median 25 m². They sold for a median 11.9% more than similar unextended houses, £1,473 for each m² added. Will an extension pay for itself here?

Medians from HM Land Registry sale prices and MHCLG Energy Performance Certificates; groups under 30 sales or 50 extended houses are not shown. These describe past sales across many homes, not a valuation of any one. How these are worked out

Next steps for your extension

Compare every council · How we calculate these figures

Get new blog posts by email

One email each time we publish a new post on project managing your build. No spam. Unsubscribe anytime.