Skip to main content
buildwiz.uk

Completion Certificates Checklist

Track which completion certificates you have obtained and which are still outstanding before your building control final inspection.

Premium calculator: included with an Access Pass

This calculator is part of the buildwiz.uk Access Pass. Get full access to every calculator and project guide, planning through to completion.

Get Access Pass

£49, paid once. 24 months access.

Already bought the Access Pass? Sign in

Before your will sign off a UK extension, you need to collect a short stack of certificates from every trade who carried out notifiable work. Building control will usually ask to see them around the building control final inspection, before it issues the , the single document a future buyer's solicitor will ask for. This checklist tracks which certificates apply to your project and which are still outstanding.

The certificates almost every extension needs

Two documents apply to nearly every extension, whatever its scope:

  • The completion certificate itself, issued by building control after the final inspection passes. You do not chase a trade for this one, the BCO produces it.
  • The under Part P, from your registered electrician, confirming the wiring meets BS 7671.

The certificates that depend on your scope

The rest are conditional. Tick the boxes above that match what you actually built, and the checklist adds the relevant items:

  • The , from an accredited SAP assessor, if building control asked for SAP calculations to show Part L compliance. Most extensions meet Part L on standard U-values instead; SAP is usually needed when the glazing exceeds 25% of the extension floor area plus the windows and doors it removes.
  • A if notifiable gas work was done, such as a new boiler or gas fire. Fitting a gas hob or cooker is not notifiable.
  • A or CERTASS certificate if windows or external doors were replaced in the existing house. Windows and doors in the new extension are covered by your building control application instead.
  • A or CCTV survey if new below-ground drainage was laid.
  • A if a boiler was fitted or replaced, which most manufacturers also require to keep the warranty valid.
  • A or acknowledgement if a party wall agreement was in place.

Miss a mandatory one and building control will usually hold back the completion certificate until it arrives. Miss a conditional one that genuinely applies and the certificate can stall for weeks after the inspection is otherwise ready.

How the timing works

Once it receives your completion notice, gives the council up to to issue the completion certificate, provided it is satisfied the work complies. The trade certificates that feed into it run on their own clocks: a Gas Safe engineer has to notify, and a scheme electrician self-certifies within . Those windows are why the paperwork often outlasts the building work, and why chasing early matters.

A worked example

Take a single-storey rear extension with a new consumer unit, a new boiler, large bi-fold doors, and a new soakaway for surface water. The glazing takes the extension past the Part L opening limit, so building control asked for a SAP calculation. Five certificates apply. The electrician issues the Electrical Installation Certificate on the day of final testing. The gas engineer registers the boiler, hands over the Boiler Benchmark checklist, and the Gas Safe compliance certificate follows by post. The groundworker's drainage test record joins the pack once the drains-before-cover stage is witnessed, and the SAP assessor produces the as-built assessment after works finish. The bi-folds need no FENSA certificate, because they sit in the new extension and building control covers them.

With those five in hand, you notify building control that the work is complete, book the final inspection, and the BCO issues the completion certificate. The trades that leave site first, the electrician and the gas engineer, are the ones to pin down in writing before they go. On one documented Oxfordshire extension the gas certificate alone took many months to prise loose, long after the family had moved back in, which is exactly the delay this checklist is meant to prevent.

The tasks, tools and materials this cost covers.

More calculators

Other free tools for this stage of your extension.

Frequently asked questions

What certificates do I need before my building control final inspection?

Almost every extension needs the building control completion certificate and an Electrical Installation Certificate under Part P. On top of those, you may need an as-built SAP energy assessment (only if building control asked for SAP calculations, usually because of large glazing), a Gas Safe compliance certificate, a FENSA or CERTASS certificate for replacement windows in the existing house, a drainage test certificate, a Boiler Benchmark checklist, or a party wall final award, depending on what work you had done. The checklist above shows which apply to your project.

How long does the council take to issue a completion certificate?

Under Regulation 17 of the Building Regulations 2010, the local authority must give the completion certificate within 8 weeks of receiving your completion notice, once it is satisfied the work complies. If the final inspection finds defects, the certificate waits until they are put right.

Why is the Gas Safe certificate always the last one to arrive?

A Gas Safe registered engineer has 30 days to notify the installation, and the compliance certificate is then posted to you separately. Waiting on a gas engineer who has moved to the next job is a common cause of completion delays. Chase them in writing the day they leave site.

Do I need a Part P certificate for extension electrics?

Yes. New circuits and a consumer unit change are notifiable under Part P, so the electrician must issue an Electrical Installation Certificate. A scheme-registered electrician self-certifies and notifies building control within 30 days. Without this document the BCO cannot sign your project off.

What if I discover no completion certificate was ever issued?

Two remediation routes exist and they are mutually exclusive: regularisation through the local authority, or indemnity insurance. Contacting the council permanently closes off the indemnity option, so decide which route fits before you make any call. Indemnity is usually faster and cheaper; regularisation is the formal route where the work was done properly but the paperwork was missed.

Doing the whole extension yourself?

Get the free budget spreadsheet. Every cost category for a UK kitchen extension, with contingency and cost per m² worked out for you.

Get the free spreadsheet

Want the full step-by-step guide, planning through to completion? See the Access Pass