buildwiz.uk

Structure

Walls, roof, steels, and making it watertight

9 tasks in this phase

Infographic of a single-storey rear extension wall labelled with four milestones: DPC level and pre-plasterboard as BCO hold points, scaffold-up at 2.4m as a construction lift, and plate height as the single Walls payment milestone, with a weather-risk indicator between construction lifts
1
Walls and Blockwork: Building Up from DPC
What happens as your extension walls go up, from DPC to plate height. Covers cavity wall construction, block types, wall ties, cavity closers, scaffolding, weather risks, and the quality checks you need to do at each payment milestone.
Free with email
Infographic showing four key steps to managing scaffold on an extension: check the quote, when scaffold goes up, agree the hire period, and the pre-removal platform inspection
2
Scaffolding
How to manage scaffolding for your extension: checking it's in the builder's quote, typical hire costs (£1,200 – £2,500), highway licences, neighbour access rights, and the pre-removal inspection that prevents expensive re-work.
Process infographic showing the steelwork journey from structural engineer specification through fabrication, delivery, and installation, with common failure points highlighted at each stage
3
Structural Steels and Lintels for Extensions
What structural steels do, who specifies them, how to verify your order, and why extension steelwork routinely exceeds initial quotes. Covers cantilevers, cavity width problems, and the ordering failures that delay builds by months.
Technical cross-section of a pitched lean-to roof structure for a single-storey extension showing wall plate, rafters with birdsmouth cuts, ridge connection, breathable membrane, and insulation layers with annotation callouts
4
Roof Structure: Getting Your Extension Watertight
How the timber roof frame goes onto your extension: wall plate, rafters, ridge, and warm roof insulation. Covers cut roofs vs trusses, the ridge beam vs ridge board distinction that catches builders out, warm roof construction, and what building control inspects before you cover anything up.
Process infographic showing the five-stage installation sequence for a pitched roof window: structural trimmed opening, window frame installation, breathable membrane with underfelt collar, tiling with flashing kit, and lead flashing with patination oil
5
Roof Windows and Rooflights
Specify, order, and install roof windows correctly for your extension. Covers Part L U-values (max 1.4 W/m²K), Part F ventilation, membrane grade, lead flashing, and the pre-scaffold inspection that prevents expensive re-work.
Process infographic showing the roof covering build sequence from breathable membrane through battens, tiles, ridge, flashing, fascia, soffit and guttering, with the extension becoming watertight at each stage
6
Roof Covering for Your Extension
What goes on top of your extension roof structure: tiles, flat roof membranes, lead flashing, dry ridge systems, fascia, soffits, and guttering. Covers the lead flashing failures that cause 90% of extension roof leaks, the roofer-window coordination problem, and a pre-payment inspection checklist no other guide gives you.
Timeline infographic showing the window ordering and installation process from specification through lead time to installation day and finishing, with key decision points and coordination milestones highlighted
7
Windows and Doors: Ordering, Lead Times, and Installation
How to specify, order, and install extension windows. Covers frame materials, glazing specs, the 8-12 week lead time trap, installation day checks, and the sealing details everyone misses.
Process infographic showing the building control structural inspection sequence: steels checked, wall ties verified, roof timbers inspected, cavity barriers confirmed, and pre-plasterboard sign-off given before any work is concealed
8
Building Control Inspection: Structure
What the BCO checks at the structural stage of your extension: steels, wall ties, cavity barriers, roof timbers, and the pre-plasterboard inspection that catches problems before they're hidden forever.
Decision flowchart showing the bifold vs sliding door choice for an extension, with key factors: opening width, sightlines, maintenance, and cost
9
Bifold and Sliding Doors for Extensions
How to choose between bifold and sliding doors for your extension, protect your money from supplier failure, and get the installation right. Aluminium bifolds from £3,150 – £7,200.

What the structure phase builds, and in what order

Groundwork left you a level base and a damp proof course. Structure gives you a building you can shut a door on.

Five jobs sit inside this phase: the walls, the steel and lintels that carry the openings, the roof frame, the roof covering, and the glazing that closes the shell. They do not run in parallel. Each hands over to the next, and the handover points are where programmes slip.

Walls and blockwork comes first, because everything downstream measures off it. Cavity walls rise off the DPC up to plate height, with wall ties and cavity closers built in as the courses go up, and every opening is set out as the blockwork passes it. An error in the setting out here carries all the way to the roofline.

Steel is next, and it behaves differently from the rest of the phase. Your structural engineer specifies the sections and connections; the fabricator then makes them to a survey taken on site, not from a drawing. That survey needs the blockwork at the right height with the supporting piers already built, so the steel order cannot be placed the day the digger leaves. If calculations are not yet issued, that sits back in structural engineer. Steels and lintels covers what happens once they are.

Only when the steels are seated and bearing properly does the roof structure go up, and only when the frame is complete does roof covering follow.

Scaffolding wraps around all of it. It goes up before any roof work starts, and it cannot come down until external finishes are done and inspected, because pointing, render, fascias and gutters are all reached from the boards. Strike it early and you pay to bring it back.

Lead times, not labour, set the length of this phase

The trades on site are rarely what holds a structure phase up. Two ordered items are.

Steel is fabricated for your building alone: cut to length, drilled, plated, primed. Once the order is placed, the queue at the fabricator is the queue, and putting more people on your site does nothing to move it. The lever you have is placing the order the moment the site survey allows, then confirming with the fabricator directly that the order exists rather than taking your builder's word for it.

Glazing runs the same way, often worse. Windows, and particularly bifold and sliding doors, are manufactured to order against a survey of the finished opening. That creates a hard dependency running the other way: structural openings cannot be formed until the final window and door sizes are confirmed. Openings get built to the manufacturer's tolerances, not the other way round. Order after the blockwork is up and you are either altering a finished opening or packing the frame out with timber filler that will always show. Windows and doors sets out the survey and order sequence.

Neither can be compressed once ordered. Both can be started early. That asymmetry is the whole game in this phase, and it is the single strongest argument for settling your openings while the trades still have weeks of work in front of them.

The inspection you cannot photograph your way past

Building control visit once during structure, and it is one of the most searching visits of the whole build. Walls up to plate height, steels and their bearings, straps and ties, cavity barriers, roof timbers: all of it has to be complete and still visible from inside at the same time. Councils call it the structural, superstructure or pre-plasterboard inspection. Same visit.

Miss it and the inspector can require the work to be opened up so it can be seen, which means stripping boarding off a wall that was finished last week, at your cost. Book it, attend it, and let nobody start closing up until it has passed. Building control inspection: structure lists what gets checked.

Weathertight is the milestone that releases everything else

The structure phase ends at weathertight: roof covered, glazing in, openings sealed. Until that point, every trade that follows is exposed to the weather, and no plasterer or electrician worth booking will commit to a firm date.

Once the shell is closed, the building stops being a site and starts being an interior. Insulation, boarding, wiring and pipework can all begin, and the programme becomes far more predictable because nothing hangs on the forecast any more. Push to reach this point before winter. A week lost before weathertight costs more than a week, because it drags every trade behind it into worse conditions.