Oxford planning statistics

Householder applications decided in the year to June 2026, compared with the rest of England.

How long does planning permission take in Oxford?

Oxford decided 42.2% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Oxford is highlighted on the map. See on the map

Within 8 weeks, no extension

42.2%

261st of 297

20.5 points slower than England

Granted

89.3%

206th of 297

1.2 points lower than England

Extension of time

54.2%

269th of 297

21.9 points higher than England

Decisions (12 months)

524

Oxford decided 524 householder applications in the year to June 2026, granting 89.3%.

42.2% were decided within 8 weeks with no extension, against 62.7% across England (261st of 297 for speed).

A further 54.2% were decided under an extension of time agreed with the applicant.

That is down from 54.6% a year earlier.

Of 14 householder appeals decided in the same period, 28.6% were allowed.

How quickly decisions are made

Oxford against England, share of householder decisions each quarter

  • Within 8 weeks, no extension
  • Extension of time
  • England, within 8 weeks
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterWithin 8 weeks, no extensionExtension of timeEngland, within 8 weeks
2008 Q192.4%0.0%89.5%
2008 Q292.0%0.0%89.4%
2008 Q393.1%0.0%89.7%
2008 Q496.5%0.0%90.3%
2009 Q196.2%0.0%90.3%
2009 Q297.3%0.0%91.7%
2009 Q396.9%0.0%91.4%
2009 Q493.8%0.0%91.0%
2010 Q193.3%0.0%88.8%
2010 Q290.5%0.0%89.8%
2010 Q393.3%0.0%88.4%
2010 Q492.5%0.0%87.7%
2011 Q187.7%0.0%86.4%
2011 Q287.4%0.0%85.9%
2011 Q386.8%0.0%84.9%
2011 Q488.2%0.0%84.9%
2012 Q188.1%0.0%83.7%
2012 Q288.6%0.0%84.2%
2012 Q387.4%0.0%82.9%
2012 Q489.0%0.0%85.2%
2013 Q191.2%0.0%85.7%
2013 Q286.0%0.0%86.3%
2013 Q380.2%0.0%85.3%
2013 Q488.9%0.0%86.3%
2014 Q190.1%0.0%85.4%
2014 Q289.6%0.0%84.9%
2014 Q370.4%0.0%82.5%
2014 Q473.9%0.0%82.1%
2015 Q178.5%0.0%80.4%
2015 Q255.6%11.7%80.6%
2015 Q370.7%20.4%79.2%
2015 Q474.0%12.3%80.0%
2016 Q137.5%25.8%78.3%
2016 Q243.8%18.2%79.8%
2016 Q353.3%12.7%77.7%
2016 Q471.8%16.4%78.0%
2017 Q176.2%19.5%77.3%
2017 Q279.6%14.2%78.5%
2017 Q386.5%11.2%76.1%
2017 Q487.8%10.8%77.1%
2018 Q184.9%12.5%73.7%
2018 Q271.4%18.8%74.0%
2018 Q371.7%25.0%72.7%
2018 Q474.5%24.2%72.7%
2019 Q180.9%14.5%69.9%
2019 Q272.5%20.2%72.1%
2019 Q376.7%20.5%69.6%
2019 Q464.2%28.3%71.5%
2020 Q169.3%26.0%68.4%
2020 Q273.1%23.9%63.9%
2020 Q363.2%30.7%63.8%
2020 Q459.0%34.6%65.3%
2021 Q160.8%33.3%59.4%
2021 Q266.3%28.6%58.4%
2021 Q354.1%44.2%53.1%
2021 Q456.8%40.8%53.0%
2022 Q146.7%49.3%51.6%
2022 Q247.3%47.3%56.0%
2022 Q347.9%44.3%53.3%
2022 Q448.6%43.7%54.1%
2023 Q145.8%49.2%53.5%
2023 Q250.3%38.8%58.5%
2023 Q355.0%40.0%59.0%
2023 Q458.6%37.5%59.8%
2024 Q162.5%32.1%58.8%
2024 Q270.8%26.9%64.4%
2024 Q363.2%31.6%64.2%
2024 Q451.2%43.3%65.6%
2025 Q153.6%44.5%62.1%
2025 Q247.8%47.8%65.0%
2025 Q336.2%60.1%62.5%
2025 Q448.3%49.0%64.7%
2026 Q137.7%60.4%60.6%
2026 Q245.3%48.9%62.7%

Share of applications granted

Oxford against England

  • Oxford
  • England
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterOxfordEngland
2008 Q183.4%85.1%
2008 Q287.1%86.1%
2008 Q377.5%86.3%
2008 Q480.6%85.3%
2009 Q185.7%85.9%
2009 Q289.1%86.8%
2009 Q392.0%87.4%
2009 Q486.9%86.9%
2010 Q186.7%87.0%
2010 Q286.0%88.0%
2010 Q389.5%87.7%
2010 Q489.4%87.5%
2011 Q189.7%87.9%
2011 Q286.8%88.5%
2011 Q391.0%88.3%
2011 Q486.3%88.3%
2012 Q188.1%88.2%
2012 Q288.1%89.2%
2012 Q381.6%89.0%
2012 Q487.8%88.9%
2013 Q189.0%89.8%
2013 Q289.9%90.6%
2013 Q391.0%90.3%
2013 Q483.7%89.6%
2014 Q195.4%89.8%
2014 Q286.3%90.5%
2014 Q392.5%90.0%
2014 Q489.8%89.2%
2015 Q189.3%89.3%
2015 Q291.3%90.2%
2015 Q389.2%90.0%
2015 Q486.3%89.2%
2016 Q187.5%90.0%
2016 Q289.2%90.3%
2016 Q386.8%90.2%
2016 Q488.7%89.7%
2017 Q189.0%89.9%
2017 Q290.7%90.5%
2017 Q389.4%90.0%
2017 Q492.6%90.1%
2018 Q190.8%90.5%
2018 Q288.3%91.0%
2018 Q391.8%91.2%
2018 Q484.2%90.5%
2019 Q191.6%90.3%
2019 Q288.8%91.0%
2019 Q391.5%90.6%
2019 Q494.2%89.8%
2020 Q186.6%89.9%
2020 Q290.3%90.2%
2020 Q391.2%90.6%
2020 Q490.4%90.3%
2021 Q190.8%90.9%
2021 Q288.3%91.2%
2021 Q392.4%91.0%
2021 Q496.0%90.1%
2022 Q194.0%90.0%
2022 Q285.6%90.4%
2022 Q396.4%89.8%
2022 Q488.0%89.4%
2023 Q187.3%89.3%
2023 Q281.0%89.2%
2023 Q380.7%88.6%
2023 Q485.9%88.2%
2024 Q184.8%88.2%
2024 Q285.4%89.1%
2024 Q381.3%89.4%
2024 Q487.4%88.6%
2025 Q180.0%89.3%
2025 Q283.5%90.4%
2025 Q389.1%90.1%
2025 Q491.6%90.1%
2026 Q192.5%90.6%
2026 Q284.7%91.0%

How long decisions took

Householder decisions over the last 12 months

  • Within 8 weeks42.2%
  • 8 to 13 weeks2.5%
  • 13 to 26 weeks1.0%
  • Over 26 weeks0.2%
  • Extension of time agreed54.2%
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
Time takenDecisions
Within 8 weeks221
8 to 13 weeks13
13 to 26 weeks5
Over 26 weeks1
Extension of time agreed284

Appeals

Decided
14
Allowed
28.6%
Median wait
11 weeks

Householder appeals to the Planning Inspectorate decided in the same 12 months. England: 34.4% allowed.

Refusals overturned at appeal

7.1% of refusals were later overturned at appeal (July 2021 to June 2026): 24 appeals allowed against 336 refusals.

89th lowest of 299 planning authorities. England: 8.9% (July 2021 to June 2026).

Householder refusals from MHCLG table PS2; appeals allowed from the Planning Inspectorate. Approximate: appeals decided in the period, which can relate to earlier refusals.

Larger home extensions (prior approval)

Single-storey rear extensions deeper than 4 metres on a detached house (3 metres otherwise), up to 8 metres (6 metres), can use prior approval instead of a planning application, except in conservation areas, National Landscapes and other protected areas.

Of 59 larger extension notifications between July 2025 and June 2026, 38 needed no approval, 2 were approved and 19 were refused.

Where Oxford had to decide, it refused 19 of 21 (90.5%), against 56.1% across England (2,210 of 3,939 decided).

Figures as first published (provisional).

MHCLG live table PDR 1.

Enforcement

2 planning enforcement notices issued in the year to June 2026.

0.03 per 1,000 homes, against 0.17 across England. 37th lowest of 294 planning authorities.

Covers all types of development, not only extensions.

MHCLG table P130; homes from the VOA Council Tax stock of properties.

Protected areas

18 conservation areas: Bartlemas, Beauchamp Lane, Binsey, Central, Headington Hill, Headington Quarry, Iffley Village, Jericho, Littlemore, Marston, North Oxford Victorian Suburb, Old Headington and 6 more.

4 Article 4 areas: Houses in Multiple Occupation Article 4 Direction, The Jericho Article 4 Direction, The Osney Town Article 4 Direction 1993 and The Wolvercote Green Article 4 Direction.

Both can remove permitted development rights, so check with the council before relying on them. Permitted development rules

To check one postcode for a conservation area, listed buildings nearby, flood zone and radon, use the address check.

planning.data.gov.uk.

Builders

295 registered building and trade firms in 2026, 4.6 per 1,000 homes, about 1.8 householder decisions per firm a year.

4th lowest of 294 planning authorities. England median: 10.1 per 1,000 homes and 0.5 decisions per firm.

Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Finding a builder

ONS UK Business Counts; homes from the VOA Council Tax stock of properties; decisions from MHCLG table PS2.

Compared with neighbouring councils

Decisions and approvals in the year to June 2026; overturns over each council's appeal window; builders per 1,000 homes in 2026.

Decided within 8 weeks, no extension

Granted

Refusals overturned at appeal

Registered building firms per 1,000 homes

Questions about planning in Oxford

How long does planning permission take in Oxford?

Oxford decided 42.2% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Is my house in a conservation area in Oxford?

18 conservation areas: Bartlemas, Beauchamp Lane, Binsey, Central, Headington Hill, Headington Quarry, Iffley Village, Jericho, Littlemore, Marston, North Oxford Victorian Suburb, Old Headington and 6 more. Most councils publish a conservation area map showing whether a street is inside one.

How many builders are there in Oxford?

295 registered building and trade firms in 2026, 4.6 per 1,000 homes, about 1.8 householder decisions per firm a year. Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Do I need planning permission for an extension in Oxford?

Many extensions can be built under permitted development without an application, but conservation areas and Article 4 directions can remove those rights, so check whether your address is in a conservation area or covered by an Article 4 direction before relying on them. Do you need planning permission?

Property prices and energy performance in Oxford

Homes sold July 2023 to June 2026, matched to the floor area and energy rating on their Energy Performance Certificate.

Median price per m²

£5,637

3,700 sales

28% above South East

Homes sold rated EPC A to C

48.8%

Median energy score 68

3.8 points below South East

Value added by extending, per m²

£3,390

19.4% on the sale price

40% above South East

Energy upgrade, no extension

+1.5%

Sale-price uplift when the energy score rose 5+ points

2.7 points below South East

The median home sold in Oxford was £450,000 for 84 m² of floor space. Price per m² is up 26% since 2015 (£4,521 to £5,681 per m², 2025). Across all 49,518 homes with a certificate, 56.1% are rated A to C on their latest one.

245 houses here were extended between two sales (second sale 2016 to 2026), adding a median 29 m². They sold for a median 19.4% more than similar unextended houses, £3,390 for each m² added. Will an extension pay for itself here?

Medians from HM Land Registry sale prices and MHCLG Energy Performance Certificates; groups under 30 sales or 50 extended houses are not shown. These describe past sales across many homes, not a valuation of any one. How these are worked out

Next steps for your extension

Compare every council · How we calculate these figures