Gateshead planning statistics

Householder applications decided in the year to June 2026, compared with the rest of England.

How long does planning permission take in Gateshead?

Gateshead decided 21.2% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Gateshead is highlighted on the map. See on the map

Within 8 weeks, no extension

21.2%

294th of 297

41.5 points slower than England

Granted

93.1%

133rd of 297

2.6 points higher than England

Extension of time

68.3%

291st of 297

36.0 points higher than England

Decisions (12 months)

259

Gateshead decided 259 householder applications in the year to June 2026, granting 93.1%.

21.2% were decided within 8 weeks with no extension, against 62.7% across England (294th of 297 for speed).

A further 68.3% were decided under an extension of time agreed with the applicant.

That is down from 29.9% a year earlier.

How quickly decisions are made

Gateshead against England, share of householder decisions each quarter

  • Within 8 weeks, no extension
  • Extension of time
  • England, within 8 weeks
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterWithin 8 weeks, no extensionExtension of timeEngland, within 8 weeks
2008 Q191.5%0.0%89.5%
2008 Q281.3%0.0%89.4%
2008 Q391.1%0.0%89.7%
2008 Q490.4%0.0%90.3%
2009 Q197.0%0.0%90.3%
2009 Q296.9%0.0%91.7%
2009 Q395.4%0.0%91.4%
2009 Q496.7%0.0%91.0%
2010 Q198.6%0.0%88.8%
2010 Q296.0%0.0%89.8%
2010 Q391.3%0.0%88.4%
2010 Q495.9%0.0%87.7%
2011 Q1100.0%0.0%86.4%
2011 Q296.3%0.0%85.9%
2011 Q391.6%0.0%84.9%
2011 Q496.7%0.0%84.9%
2012 Q191.8%0.0%83.7%
2012 Q293.4%0.0%84.2%
2012 Q396.9%0.0%82.9%
2012 Q490.4%0.0%85.2%
2013 Q197.4%0.0%85.7%
2013 Q296.7%0.0%86.3%
2013 Q392.2%0.0%85.3%
2013 Q496.0%0.0%86.3%
2014 Q195.7%0.0%85.4%
2014 Q291.4%0.0%84.9%
2014 Q391.9%0.0%82.5%
2014 Q492.2%0.0%82.1%
2015 Q198.0%0.0%80.4%
2015 Q289.7%0.0%80.6%
2015 Q390.5%0.0%79.2%
2015 Q491.4%0.0%80.0%
2016 Q172.7%3.6%78.3%
2016 Q291.1%3.7%79.8%
2016 Q385.4%8.7%77.7%
2016 Q487.7%9.4%78.0%
2017 Q171.4%17.9%77.3%
2017 Q264.3%28.0%78.5%
2017 Q343.8%31.5%76.1%
2017 Q458.5%27.4%77.1%
2018 Q178.6%16.2%73.7%
2018 Q280.7%14.7%74.0%
2018 Q376.6%20.3%72.7%
2018 Q477.9%14.0%72.7%
2019 Q171.3%20.2%69.9%
2019 Q288.2%8.5%72.1%
2019 Q381.9%15.3%69.6%
2019 Q487.9%9.1%71.5%
2020 Q184.5%12.7%68.4%
2020 Q260.0%22.9%63.9%
2020 Q350.0%27.0%63.8%
2020 Q445.4%30.3%65.3%
2021 Q143.6%36.8%59.4%
2021 Q243.2%22.8%58.4%
2021 Q336.7%23.8%53.1%
2021 Q437.4%48.8%53.0%
2022 Q132.6%57.3%51.6%
2022 Q229.7%58.4%56.0%
2022 Q316.5%82.4%53.3%
2022 Q46.7%92.0%54.1%
2023 Q19.6%85.5%53.5%
2023 Q210.8%82.4%58.5%
2023 Q324.6%73.8%59.0%
2023 Q426.9%64.1%59.8%
2024 Q136.4%54.5%58.8%
2024 Q247.7%41.5%64.4%
2024 Q329.3%58.7%64.2%
2024 Q425.0%65.0%65.6%
2025 Q118.5%63.0%62.1%
2025 Q242.7%54.7%65.0%
2025 Q317.1%75.0%62.5%
2025 Q423.1%61.5%64.7%
2026 Q116.7%77.8%60.6%
2026 Q228.1%59.4%62.7%

Share of applications granted

Gateshead against England

  • Gateshead
  • England
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterGatesheadEngland
2008 Q192.3%85.1%
2008 Q293.0%86.1%
2008 Q394.1%86.3%
2008 Q494.1%85.3%
2009 Q185.0%85.9%
2009 Q292.9%86.8%
2009 Q389.9%87.4%
2009 Q488.4%86.9%
2010 Q195.8%87.0%
2010 Q292.8%88.0%
2010 Q393.9%87.7%
2010 Q498.3%87.5%
2011 Q193.1%87.9%
2011 Q298.1%88.5%
2011 Q391.0%88.3%
2011 Q495.8%88.3%
2012 Q190.8%88.2%
2012 Q297.1%89.2%
2012 Q393.9%89.0%
2012 Q492.3%88.9%
2013 Q197.4%89.8%
2013 Q296.7%90.6%
2013 Q392.2%90.3%
2013 Q496.0%89.6%
2014 Q190.3%89.8%
2014 Q294.1%90.5%
2014 Q395.5%90.0%
2014 Q499.0%89.2%
2015 Q195.9%89.3%
2015 Q298.3%90.2%
2015 Q395.8%90.0%
2015 Q495.1%89.2%
2016 Q195.5%90.0%
2016 Q294.1%90.3%
2016 Q398.1%90.2%
2016 Q495.3%89.7%
2017 Q195.2%89.9%
2017 Q297.2%90.5%
2017 Q399.2%90.0%
2017 Q496.3%90.1%
2018 Q196.6%90.5%
2018 Q296.7%91.0%
2018 Q393.8%91.2%
2018 Q497.8%90.5%
2019 Q190.4%90.3%
2019 Q297.4%91.0%
2019 Q393.1%90.6%
2019 Q497.0%89.8%
2020 Q197.2%89.9%
2020 Q297.1%90.2%
2020 Q397.6%90.6%
2020 Q495.8%90.3%
2021 Q194.9%90.9%
2021 Q297.5%91.2%
2021 Q396.6%91.0%
2021 Q495.1%90.1%
2022 Q197.8%90.0%
2022 Q297.0%90.4%
2022 Q3100.0%89.8%
2022 Q4100.0%89.4%
2023 Q1100.0%89.3%
2023 Q297.3%89.2%
2023 Q396.9%88.6%
2023 Q496.2%88.2%
2024 Q190.9%88.2%
2024 Q298.5%89.1%
2024 Q397.3%89.4%
2024 Q493.3%88.6%
2025 Q1100.0%89.3%
2025 Q297.3%90.4%
2025 Q393.4%90.1%
2025 Q493.8%90.1%
2026 Q192.6%90.6%
2026 Q292.2%91.0%

How long decisions took

Householder decisions over the last 12 months

  • Within 8 weeks21.2%
  • 8 to 13 weeks3.9%
  • 13 to 26 weeks2.3%
  • Over 26 weeks4.2%
  • Extension of time agreed68.3%
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
Time takenDecisions
Within 8 weeks55
8 to 13 weeks10
13 to 26 weeks6
Over 26 weeks11
Extension of time agreed177

Appeals

Decided
3
Allowed
0.0%
Median wait
12 weeks

Householder appeals to the Planning Inspectorate decided in the same 12 months. England: 34.4% allowed.

Refusals overturned at appeal

9.8% of refusals were later overturned at appeal (July 2021 to June 2026): 6 appeals allowed against 56 refusals.

Split decisions count as half.

106th highest of 299 planning authorities. England: 8.9% (July 2021 to June 2026).

Householder refusals from MHCLG table PS2; appeals allowed from the Planning Inspectorate. Approximate: appeals decided in the period, which can relate to earlier refusals.

Larger home extensions (prior approval)

Single-storey rear extensions deeper than 4 metres on a detached house (3 metres otherwise), up to 8 metres (6 metres), can use prior approval instead of a planning application, except in conservation areas, National Landscapes and other protected areas.

Of 3 larger extension notifications between July 2025 and June 2026, 3 needed no approval, 0 were approved and 0 were refused.

Fewer than 10 decided in the period.

Figures as first published (provisional).

MHCLG live table PDR 1.

Enforcement

2 planning enforcement notices issued in the year to June 2026.

0.02 per 1,000 homes, against 0.17 across England. 20th lowest of 294 planning authorities.

Covers all types of development, not only extensions.

MHCLG table P130; homes from the VOA Council Tax stock of properties.

Protected areas

Gateshead has not published its conservation area boundaries to the national planning data service, so the count may be incomplete.

5 Article 4 areas: Saltwell Conservation Area Article 4 Direction 1, Saltwell Conservation Area Article 4 Direction 2, Saltwell Conservation Area Article 4 Direction 3, Saltwell Conservation Area Article 4 Direction 4 and Saltwell Conservation Area Article 4 Direction 5.

Both can remove permitted development rights, so check with the council before relying on them. Permitted development rules

To check one postcode for a conservation area, listed buildings nearby, flood zone and radon, use the address check.

planning.data.gov.uk.

Builders

705 registered building and trade firms in 2026, 7.3 per 1,000 homes, about 0.4 householder decisions per firm a year.

43rd lowest of 294 planning authorities. England median: 10.1 per 1,000 homes and 0.5 decisions per firm.

Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Finding a builder

ONS UK Business Counts; homes from the VOA Council Tax stock of properties; decisions from MHCLG table PS2.

Compared with neighbouring councils

Decisions and approvals in the year to June 2026; overturns over each council's appeal window; builders per 1,000 homes in 2026.

Decided within 8 weeks, no extension

Granted

Refusals overturned at appeal

Registered building firms per 1,000 homes

Questions about planning in Gateshead

How long does planning permission take in Gateshead?

Gateshead decided 21.2% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Is my house in a conservation area in Gateshead?

Gateshead has not published its conservation area boundaries to the national planning data service, so the count may be incomplete. Most councils publish a conservation area map showing whether a street is inside one.

How many builders are there in Gateshead?

705 registered building and trade firms in 2026, 7.3 per 1,000 homes, about 0.4 householder decisions per firm a year. Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Do I need planning permission for an extension in Gateshead?

Many extensions can be built under permitted development without an application, but conservation areas and Article 4 directions can remove those rights, so check whether your address is in a conservation area or covered by an Article 4 direction before relying on them. Do you need planning permission?

Property prices and energy performance in Gateshead

Homes sold July 2023 to June 2026, matched to the floor area and energy rating on their Energy Performance Certificate.

Median price per m²

£2,035

7,425 sales

In line with North East

Homes sold rated EPC A to C

52.9%

Median energy score 69

1.4 points below North East

Value added by extending, per m²

£825

10.5% on the sale price

19% below North East

Energy upgrade, no extension

+2.8%

Sale-price uplift when the energy score rose 5+ points

5.2 points below North East

The median home sold in Gateshead was £162,000 for 82 m² of floor space. Price per m² is up 29% since 2015 (£1,605 to £2,067 per m², 2025). Across all 66,384 homes with a certificate, 49.9% are rated A to C on their latest one.

212 houses here were extended between two sales (second sale 2016 to 2026), adding a median 29 m². They sold for a median 10.5% more than similar unextended houses, £825 for each m² added. Will an extension pay for itself here?

Medians from HM Land Registry sale prices and MHCLG Energy Performance Certificates; groups under 30 sales or 50 extended houses are not shown. These describe past sales across many homes, not a valuation of any one. How these are worked out

Next steps for your extension