Ebbsfleet Development Corporation planning statistics

Householder applications decided in the year to June 2026, compared with the rest of England.

How long does planning permission take in Ebbsfleet Development Corporation?

Ebbsfleet Development Corporation decided 78.6% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Ebbsfleet Development Corporation is highlighted on the map. See on the map

Within 8 weeks, no extension

78.6%

15.9 points faster than England

Granted

100.0%

9.5 points higher than England

Extension of time

14.3%

18.0 points lower than England

Decisions (12 months)

14

Ebbsfleet Development Corporation decided 14 householder applications in the year to June 2026, granting 100.0%.

Too few decisions are made here to rank the council fairly against others.

A further 14.3% were decided under an extension of time agreed with the applicant.

How quickly decisions are made

Ebbsfleet Development Corporation against England, share of householder decisions each quarter

  • Within 8 weeks, no extension
  • Extension of time
  • England, within 8 weeks
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterWithin 8 weeks, no extensionExtension of timeEngland, within 8 weeks
2015 Q3––79.2%
2015 Q4––80.0%
2016 Q1––78.3%
2016 Q2100.0%0.0%79.8%
2016 Q3––77.7%
2016 Q4––78.0%
2017 Q1––77.3%
2017 Q2––78.5%
2017 Q3100.0%0.0%76.1%
2017 Q4––77.1%
2018 Q150.0%50.0%73.7%
2018 Q2––74.0%
2018 Q3100.0%0.0%72.7%
2018 Q4100.0%0.0%72.7%
2019 Q166.7%33.3%69.9%
2019 Q2100.0%0.0%72.1%
2019 Q333.3%66.7%69.6%
2019 Q4100.0%0.0%71.5%
2020 Q1100.0%0.0%68.4%
2020 Q2100.0%0.0%63.9%
2020 Q380.0%20.0%63.8%
2020 Q4100.0%0.0%65.3%
2021 Q160.0%20.0%59.4%
2021 Q270.0%10.0%58.4%
2021 Q380.0%20.0%53.1%
2021 Q4100.0%0.0%53.0%
2022 Q183.3%16.7%51.6%
2022 Q2100.0%0.0%56.0%
2022 Q380.0%20.0%53.3%
2022 Q440.0%60.0%54.1%
2023 Q183.3%16.7%53.5%
2023 Q2100.0%0.0%58.5%
2023 Q3100.0%0.0%59.0%
2023 Q487.5%12.5%59.8%
2024 Q175.0%25.0%58.8%
2024 Q2100.0%0.0%64.4%
2024 Q350.0%33.3%64.2%
2024 Q4100.0%0.0%65.6%
2025 Q162.5%37.5%62.1%
2025 Q277.8%22.2%65.0%
2025 Q375.0%25.0%62.5%
2025 Q466.7%33.3%64.7%
2026 Q166.7%0.0%60.6%
2026 Q2100.0%0.0%62.7%

Share of applications granted

Ebbsfleet Development Corporation against England

  • Ebbsfleet Development Corporation
  • England
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterEbbsfleet Development CorporationEngland
2015 Q3–90.0%
2015 Q4–89.2%
2016 Q1–90.0%
2016 Q2100.0%90.3%
2016 Q3–90.2%
2016 Q4–89.7%
2017 Q1–89.9%
2017 Q2–90.5%
2017 Q3100.0%90.0%
2017 Q4–90.1%
2018 Q1100.0%90.5%
2018 Q2–91.0%
2018 Q3100.0%91.2%
2018 Q4100.0%90.5%
2019 Q1100.0%90.3%
2019 Q2100.0%91.0%
2019 Q3100.0%90.6%
2019 Q4100.0%89.8%
2020 Q1100.0%89.9%
2020 Q2100.0%90.2%
2020 Q3100.0%90.6%
2020 Q4100.0%90.3%
2021 Q1100.0%90.9%
2021 Q290.0%91.2%
2021 Q3100.0%91.0%
2021 Q4100.0%90.1%
2022 Q183.3%90.0%
2022 Q2100.0%90.4%
2022 Q3100.0%89.8%
2022 Q4100.0%89.4%
2023 Q1100.0%89.3%
2023 Q2100.0%89.2%
2023 Q366.7%88.6%
2023 Q4100.0%88.2%
2024 Q1100.0%88.2%
2024 Q2100.0%89.1%
2024 Q383.3%89.4%
2024 Q4100.0%88.6%
2025 Q187.5%89.3%
2025 Q2100.0%90.4%
2025 Q3100.0%90.1%
2025 Q4100.0%90.1%
2026 Q1100.0%90.6%
2026 Q2100.0%91.0%

How long decisions took

Householder decisions over the last 12 months

  • Within 8 weeks78.6%
  • 8 to 13 weeks7.1%
  • 13 to 26 weeks0.0%
  • Over 26 weeks0.0%
  • Extension of time agreed14.3%
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
Time takenDecisions
Within 8 weeks11
8 to 13 weeks1
13 to 26 weeks0
Over 26 weeks0
Extension of time agreed2

Appeals

No householder appeals were decided in this period.

Householder appeals to the Planning Inspectorate decided in the same 12 months. England: 34.4% allowed.

Refusals overturned at appeal

Too few refusals to measure reliably.

England: 8.9% (July 2021 to June 2026).

Householder refusals from MHCLG table PS2; appeals allowed from the Planning Inspectorate. Approximate: appeals decided in the period, which can relate to earlier refusals.

Larger home extensions (prior approval)

Single-storey rear extensions deeper than 4 metres on a detached house (3 metres otherwise), up to 8 metres (6 metres), can use prior approval instead of a planning application, except in conservation areas, National Landscapes and other protected areas.

Of 0 larger extension notifications between July 2025 and June 2026, 0 needed no approval, 0 were approved and 0 were refused.

Fewer than 10 decided in the period.

Figures as first published (provisional).

MHCLG live table PDR 1.

Enforcement

1 planning enforcement notice issued in the year to June 2026.

Per-home figures are not available for development corporations.

Covers all types of development, not only extensions.

MHCLG table P130; homes from the VOA Council Tax stock of properties.

Protected areas

Ebbsfleet Development Corporation has not published its conservation area boundaries to the national planning data service, so the count may be incomplete.

Ebbsfleet Development Corporation has not published its Article 4 directions to the national planning data service, so the count may be incomplete.

Both can remove permitted development rights, so check with the council before relying on them. Permitted development rules

To check one postcode for a conservation area, listed buildings nearby, flood zone and radon, use the address check.

planning.data.gov.uk.

Builders

Builder counts are not available for development corporations.

Finding a builder

ONS UK Business Counts; homes from the VOA Council Tax stock of properties; decisions from MHCLG table PS2.

Compared with neighbouring councils

Decisions and approvals in the year to June 2026; overturns over each council's appeal window; builders per 1,000 homes in 2026.

Decided within 8 weeks, no extension

Granted

Refusals overturned at appeal

Registered building firms per 1,000 homes

Questions about planning in Ebbsfleet Development Corporation

How long does planning permission take in Ebbsfleet Development Corporation?

Ebbsfleet Development Corporation decided 78.6% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Is my house in a conservation area in Ebbsfleet Development Corporation?

Ebbsfleet Development Corporation has not published its conservation area boundaries to the national planning data service, so the count may be incomplete. Most councils publish a conservation area map showing whether a street is inside one.

How many builders are there in Ebbsfleet Development Corporation?

Builder counts are not available for development corporations.

Do I need planning permission for an extension in Ebbsfleet Development Corporation?

Many extensions can be built under permitted development without an application, but conservation areas and Article 4 directions can remove those rights, so check whether your address is in a conservation area or covered by an Article 4 direction before relying on them. Do you need planning permission?

Next steps for your extension

Compare every council · How we calculate these figures