East Lindsey planning statistics

Householder applications decided in the year to June 2026, compared with the rest of England.

How long does planning permission take in East Lindsey?

East Lindsey decided 59.0% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

East Lindsey is highlighted on the map. See on the map

Within 8 weeks, no extension

59.0%

188th of 297

3.7 points slower than England

Granted

94.7%

93rd of 297

4.2 points higher than England

Extension of time

38.1%

203rd of 297

5.8 points higher than England

Decisions (12 months)

244

East Lindsey decided 244 householder applications in the year to June 2026, granting 94.7%.

59.0% were decided within 8 weeks with no extension, against 62.7% across England (188th of 297 for speed).

A further 38.1% were decided under an extension of time agreed with the applicant.

That is down from 63.7% a year earlier.

How quickly decisions are made

East Lindsey against England, share of householder decisions each quarter

  • Within 8 weeks, no extension
  • Extension of time
  • England, within 8 weeks
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterWithin 8 weeks, no extensionExtension of timeEngland, within 8 weeks
2008 Q196.5%0.0%89.5%
2008 Q295.3%0.0%89.4%
2008 Q397.7%0.0%89.7%
2008 Q494.9%0.0%90.3%
2009 Q197.8%0.0%90.3%
2009 Q295.3%0.0%91.7%
2009 Q395.5%0.0%91.4%
2009 Q493.1%0.0%91.0%
2010 Q198.1%0.0%88.8%
2010 Q298.3%0.0%89.8%
2010 Q398.2%0.0%88.4%
2010 Q497.6%0.0%87.7%
2011 Q195.9%0.0%86.4%
2011 Q295.1%0.0%85.9%
2011 Q396.6%0.0%84.9%
2011 Q498.0%0.0%84.9%
2012 Q196.9%0.0%83.7%
2012 Q290.4%0.0%84.2%
2012 Q391.0%0.0%82.9%
2012 Q499.0%0.0%85.2%
2013 Q192.2%0.0%85.7%
2013 Q296.7%0.0%86.3%
2013 Q397.9%0.0%85.3%
2013 Q486.4%0.0%86.3%
2014 Q191.0%0.0%85.4%
2014 Q294.7%0.0%84.9%
2014 Q397.0%0.0%82.5%
2014 Q496.7%1.1%82.1%
2015 Q187.9%2.2%80.4%
2015 Q290.1%6.9%80.6%
2015 Q395.6%4.4%79.2%
2015 Q498.9%1.1%80.0%
2016 Q192.3%7.7%78.3%
2016 Q288.8%10.5%79.8%
2016 Q390.4%8.8%77.7%
2016 Q493.9%6.1%78.0%
2017 Q191.7%8.3%77.3%
2017 Q292.8%7.2%78.5%
2017 Q382.4%17.6%76.1%
2017 Q491.0%9.0%77.1%
2018 Q193.9%6.1%73.7%
2018 Q290.8%9.2%74.0%
2018 Q386.1%13.9%72.7%
2018 Q485.7%14.3%72.7%
2019 Q190.5%9.5%69.9%
2019 Q290.6%9.4%72.1%
2019 Q391.0%9.0%69.6%
2019 Q491.0%9.0%71.5%
2020 Q187.5%12.5%68.4%
2020 Q289.1%10.9%63.9%
2020 Q389.4%10.6%63.8%
2020 Q490.4%9.6%65.3%
2021 Q192.8%7.2%59.4%
2021 Q290.6%9.4%58.4%
2021 Q381.9%15.3%53.1%
2021 Q478.1%18.1%53.0%
2022 Q170.4%21.4%51.6%
2022 Q272.6%25.8%56.0%
2022 Q377.1%18.3%53.3%
2022 Q460.7%33.7%54.1%
2023 Q151.6%35.2%53.5%
2023 Q281.9%18.1%58.5%
2023 Q360.9%31.0%59.0%
2023 Q468.8%23.4%59.8%
2024 Q165.8%31.6%58.8%
2024 Q268.4%28.4%64.4%
2024 Q367.8%28.8%64.2%
2024 Q467.6%29.4%65.6%
2025 Q162.5%31.3%62.1%
2025 Q259.1%32.3%65.0%
2025 Q370.4%27.2%62.5%
2025 Q470.6%25.5%64.7%
2026 Q138.6%56.1%60.6%
2026 Q252.7%47.3%62.7%

Share of applications granted

East Lindsey against England

  • East Lindsey
  • England
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterEast LindseyEngland
2008 Q189.0%85.1%
2008 Q289.4%86.1%
2008 Q387.9%86.3%
2008 Q489.1%85.3%
2009 Q184.4%85.9%
2009 Q293.8%86.8%
2009 Q384.3%87.4%
2009 Q492.4%86.9%
2010 Q181.3%87.0%
2010 Q283.6%88.0%
2010 Q386.8%87.7%
2010 Q488.9%87.5%
2011 Q189.7%87.9%
2011 Q285.3%88.5%
2011 Q388.2%88.3%
2011 Q489.1%88.3%
2012 Q191.8%88.2%
2012 Q289.4%89.2%
2012 Q397.0%89.0%
2012 Q496.9%88.9%
2013 Q193.8%89.8%
2013 Q293.5%90.6%
2013 Q397.9%90.3%
2013 Q493.8%89.6%
2014 Q194.9%89.8%
2014 Q295.7%90.5%
2014 Q392.0%90.0%
2014 Q495.6%89.2%
2015 Q198.9%89.3%
2015 Q297.0%90.2%
2015 Q394.5%90.0%
2015 Q4100.0%89.2%
2016 Q196.2%90.0%
2016 Q292.3%90.3%
2016 Q396.3%90.2%
2016 Q499.1%89.7%
2017 Q194.8%89.9%
2017 Q297.6%90.5%
2017 Q393.4%90.0%
2017 Q495.5%90.1%
2018 Q193.9%90.5%
2018 Q298.2%91.0%
2018 Q396.3%91.2%
2018 Q497.6%90.5%
2019 Q1100.0%90.3%
2019 Q299.1%91.0%
2019 Q3100.0%90.6%
2019 Q497.8%89.8%
2020 Q197.5%89.9%
2020 Q298.0%90.2%
2020 Q399.0%90.6%
2020 Q499.0%90.3%
2021 Q197.9%90.9%
2021 Q299.3%91.2%
2021 Q397.9%91.0%
2021 Q497.1%90.1%
2022 Q199.0%90.0%
2022 Q2100.0%90.4%
2022 Q3100.0%89.8%
2022 Q497.8%89.4%
2023 Q196.7%89.3%
2023 Q2100.0%89.2%
2023 Q396.6%88.6%
2023 Q497.4%88.2%
2024 Q197.4%88.2%
2024 Q2100.0%89.1%
2024 Q398.3%89.4%
2024 Q495.6%88.6%
2025 Q196.9%89.3%
2025 Q292.5%90.4%
2025 Q393.8%90.1%
2025 Q492.2%90.1%
2026 Q198.2%90.6%
2026 Q294.5%91.0%

How long decisions took

Householder decisions over the last 12 months

  • Within 8 weeks59.0%
  • 8 to 13 weeks2.0%
  • 13 to 26 weeks0.8%
  • Over 26 weeks0.0%
  • Extension of time agreed38.1%
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
Time takenDecisions
Within 8 weeks144
8 to 13 weeks5
13 to 26 weeks2
Over 26 weeks0
Extension of time agreed93

Appeals

Decided
3
Allowed
0.0%
Median wait
9 weeks

Householder appeals to the Planning Inspectorate decided in the same 12 months. England: 34.4% allowed.

Refusals overturned at appeal

1.1% of refusals were later overturned at appeal (July 2021 to June 2026): 1 appeal allowed against 45 refusals.

Split decisions count as half.

3rd lowest of 299 planning authorities. England: 8.9% (July 2021 to June 2026).

Householder refusals from MHCLG table PS2; appeals allowed from the Planning Inspectorate. Approximate: appeals decided in the period, which can relate to earlier refusals.

Larger home extensions (prior approval)

Single-storey rear extensions deeper than 4 metres on a detached house (3 metres otherwise), up to 8 metres (6 metres), can use prior approval instead of a planning application, except in conservation areas, National Landscapes and other protected areas.

Of 9 larger extension notifications between July 2025 and June 2026, 9 needed no approval, 0 were approved and 0 were refused.

Fewer than 10 decided in the period.

Figures as first published (provisional).

MHCLG live table PDR 1.

Enforcement

11 planning enforcement notices issued in the year to June 2026.

0.15 per 1,000 homes, against 0.17 across England. 92nd highest of 294 planning authorities.

Covers all types of development, not only extensions.

MHCLG table P130; homes from the VOA Council Tax stock of properties.

Protected areas

17 conservation areas: Alford, Binbrook, Burgh le Marsh, Horncastle, Hundleby, Louth, North Thoresby, Old Bolingbroke, Raithby, Revesby, South Willingham, Spilsby and 5 more.

East Lindsey has not published its Article 4 directions to the national planning data service, so the count may be incomplete.

Both can remove permitted development rights, so check with the council before relying on them. Permitted development rules

To check one postcode for a conservation area, listed buildings nearby, flood zone and radon, use the address check.

planning.data.gov.uk.

Builders

595 registered building and trade firms in 2026, 8.1 per 1,000 homes, about 0.4 householder decisions per firm a year.

69th lowest of 294 planning authorities. England median: 10.1 per 1,000 homes and 0.5 decisions per firm.

Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Finding a builder

ONS UK Business Counts; homes from the VOA Council Tax stock of properties; decisions from MHCLG table PS2.

Compared with neighbouring councils

Decisions and approvals in the year to June 2026; overturns over each council's appeal window; builders per 1,000 homes in 2026.

Decided within 8 weeks, no extension

Granted

Refusals overturned at appeal

Registered building firms per 1,000 homes

Questions about planning in East Lindsey

How long does planning permission take in East Lindsey?

East Lindsey decided 59.0% of householder applications within 8 weeks without an extension in the year to June 2026, against 62.7% across England.

Is my house in a conservation area in East Lindsey?

17 conservation areas: Alford, Binbrook, Burgh le Marsh, Horncastle, Hundleby, Louth, North Thoresby, Old Bolingbroke, Raithby, Revesby, South Willingham, Spilsby and 5 more. Most councils publish a conservation area map showing whether a street is inside one.

How many builders are there in East Lindsey?

595 registered building and trade firms in 2026, 8.1 per 1,000 homes, about 0.4 householder decisions per firm a year. Counts VAT or PAYE registered firms only, rounded to 5 by ONS; self-employed builders below the VAT threshold aren't included.

Do I need planning permission for an extension in East Lindsey?

Many extensions can be built under permitted development without an application, but conservation areas and Article 4 directions can remove those rights, so check whether your address is in a conservation area or covered by an Article 4 direction before relying on them. Do you need planning permission?

Property prices and energy performance in East Lindsey

Homes sold July 2023 to June 2026, matched to the floor area and energy rating on their Energy Performance Certificate.

Median price per m²

£2,455

6,053 sales

14% below East Midlands

Homes sold rated EPC A to C

45.0%

Median energy score 67

6.8 points below East Midlands

Value added by extending, per m²

£1,182

17.4% on the sale price

24% below East Midlands

Energy upgrade, no extension

+7.3%

Sale-price uplift when the energy score rose 5+ points

0.9 points above East Midlands

The median home sold in East Lindsey was £216,000 for 88 m² of floor space. Price per m² is up 49% since 2015 (£1,657 to £2,475 per m², 2025). Across all 54,355 homes with a certificate, 40.3% are rated A to C on their latest one.

338 houses here were extended between two sales (second sale 2016 to 2026), adding a median 30 m². They sold for a median 17.4% more than similar unextended houses, £1,182 for each m² added. Will an extension pay for itself here?

Medians from HM Land Registry sale prices and MHCLG Energy Performance Certificates; groups under 30 sales or 50 extended houses are not shown. These describe past sales across many homes, not a valuation of any one. How these are worked out

Next steps for your extension