Bedford planning statistics

Householder applications decided in the year to June 2026, compared with the rest of England.

Within 8 weeks, no extension

58.0%

192nd of 297

4.7 points slower than England

Granted

87.6%

229th of 297

2.9 points lower than England

Extension of time

37.0%

198th of 297

4.7 points higher than England

Decisions (12 months)

548

Bedford decided 548 householder applications in the year to June 2026, granting 87.6%.

58.0% were decided within 8 weeks with no extension, against 62.7% across England (192nd of 297 for speed).

A further 37.0% were decided under an extension of time agreed with the applicant.

That is up from 53.0% a year earlier.

Of 15 householder appeals decided in the same period, 33.3% were allowed.

How quickly decisions are made

Bedford against England, share of householder decisions each quarter

  • Within 8 weeks, no extension
  • Extension of time
  • England, within 8 weeks
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterWithin 8 weeks, no extensionExtension of timeEngland, within 8 weeks
2008 Q191.3%0.0%89.5%
2008 Q291.7%0.0%89.4%
2008 Q390.5%0.0%89.7%
2008 Q488.4%0.0%90.3%
2009 Q195.6%0.0%90.3%
2009 Q292.0%0.0%91.7%
2009 Q389.1%0.0%91.4%
2009 Q493.5%0.0%91.0%
2010 Q195.3%0.0%88.8%
2010 Q292.0%0.0%89.8%
2010 Q390.2%0.0%88.4%
2010 Q489.4%0.0%87.7%
2011 Q190.8%0.0%86.4%
2011 Q291.3%0.0%85.9%
2011 Q391.3%0.0%84.9%
2011 Q489.7%0.0%84.9%
2012 Q189.0%0.0%83.7%
2012 Q288.0%0.0%84.2%
2012 Q392.4%0.0%82.9%
2012 Q489.0%0.0%85.2%
2013 Q183.1%0.0%85.7%
2013 Q290.8%0.0%86.3%
2013 Q389.5%0.0%85.3%
2013 Q484.3%0.0%86.3%
2014 Q184.1%0.0%85.4%
2014 Q287.6%0.0%84.9%
2014 Q386.4%0.0%82.5%
2014 Q490.2%0.6%82.1%
2015 Q189.6%4.5%80.4%
2015 Q283.4%6.7%80.6%
2015 Q380.4%10.6%79.2%
2015 Q486.5%8.0%80.0%
2016 Q185.7%5.8%78.3%
2016 Q268.4%5.3%79.8%
2016 Q356.8%15.1%77.7%
2016 Q475.1%16.1%78.0%
2017 Q184.9%12.9%77.3%
2017 Q283.4%15.2%78.5%
2017 Q382.3%12.9%76.1%
2017 Q486.4%9.7%77.1%
2018 Q178.1%15.6%73.7%
2018 Q274.3%17.4%74.0%
2018 Q355.9%26.3%72.7%
2018 Q463.7%28.5%72.7%
2019 Q152.3%42.5%69.9%
2019 Q244.3%44.3%72.1%
2019 Q340.6%45.3%69.6%
2019 Q458.0%30.5%71.5%
2020 Q148.3%34.7%68.4%
2020 Q238.5%43.6%63.9%
2020 Q333.0%52.7%63.8%
2020 Q438.6%41.4%65.3%
2021 Q138.1%47.7%59.4%
2021 Q243.0%43.4%58.4%
2021 Q331.9%52.7%53.1%
2021 Q428.1%47.5%53.0%
2022 Q141.4%37.4%51.6%
2022 Q242.6%41.4%56.0%
2022 Q355.7%30.7%53.3%
2022 Q458.1%33.0%54.1%
2023 Q162.4%26.0%53.5%
2023 Q269.3%26.0%58.5%
2023 Q364.8%29.0%59.0%
2023 Q474.1%22.9%59.8%
2024 Q169.2%25.0%58.8%
2024 Q271.3%24.0%64.4%
2024 Q346.5%43.9%64.2%
2024 Q454.0%40.0%65.6%
2025 Q158.2%40.4%62.1%
2025 Q253.9%40.3%65.0%
2025 Q352.5%46.1%62.5%
2025 Q464.1%34.4%64.7%
2026 Q155.9%35.1%60.6%
2026 Q259.5%32.7%62.7%

Share of applications granted

Bedford against England

  • Bedford
  • England
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
QuarterBedfordEngland
2008 Q180.4%85.1%
2008 Q281.8%86.1%
2008 Q379.7%86.3%
2008 Q485.1%85.3%
2009 Q185.3%85.9%
2009 Q284.7%86.8%
2009 Q385.2%87.4%
2009 Q488.4%86.9%
2010 Q186.5%87.0%
2010 Q288.0%88.0%
2010 Q390.7%87.7%
2010 Q491.4%87.5%
2011 Q195.0%87.9%
2011 Q290.8%88.5%
2011 Q391.3%88.3%
2011 Q491.9%88.3%
2012 Q189.0%88.2%
2012 Q293.1%89.2%
2012 Q389.0%89.0%
2012 Q492.5%88.9%
2013 Q191.9%89.8%
2013 Q292.6%90.6%
2013 Q392.8%90.3%
2013 Q494.8%89.6%
2014 Q194.9%89.8%
2014 Q295.5%90.5%
2014 Q393.8%90.0%
2014 Q495.7%89.2%
2015 Q197.0%89.3%
2015 Q291.7%90.2%
2015 Q387.7%90.0%
2015 Q489.6%89.2%
2016 Q192.9%90.0%
2016 Q293.7%90.3%
2016 Q392.2%90.2%
2016 Q494.0%89.7%
2017 Q187.1%89.9%
2017 Q295.7%90.5%
2017 Q393.1%90.0%
2017 Q488.1%90.1%
2018 Q190.6%90.5%
2018 Q289.0%91.0%
2018 Q387.2%91.2%
2018 Q489.4%90.5%
2019 Q188.9%90.3%
2019 Q292.3%91.0%
2019 Q388.0%90.6%
2019 Q483.3%89.8%
2020 Q186.4%89.9%
2020 Q285.3%90.2%
2020 Q379.7%90.6%
2020 Q486.0%90.3%
2021 Q181.6%90.9%
2021 Q286.3%91.2%
2021 Q386.1%91.0%
2021 Q483.1%90.1%
2022 Q182.8%90.0%
2022 Q284.5%90.4%
2022 Q383.0%89.8%
2022 Q483.2%89.4%
2023 Q178.5%89.3%
2023 Q282.3%89.2%
2023 Q385.2%88.6%
2023 Q474.7%88.2%
2024 Q182.7%88.2%
2024 Q281.4%89.1%
2024 Q384.5%89.4%
2024 Q486.7%88.6%
2025 Q187.2%89.3%
2025 Q286.4%90.4%
2025 Q391.5%90.1%
2025 Q485.9%90.1%
2026 Q180.2%90.6%
2026 Q290.5%91.0%

How long decisions took

Householder decisions over the last 12 months

  • Within 8 weeks58.0%
  • 8 to 13 weeks4.2%
  • 13 to 26 weeks0.5%
  • Over 26 weeks0.2%
  • Extension of time agreed37.0%
Source: MHCLG PS2, OGL v3. Chart: buildwiz.uk
Show data
Time takenDecisions
Within 8 weeks318
8 to 13 weeks23
13 to 26 weeks3
Over 26 weeks1
Extension of time agreed203

Appeals

Decided
15
Allowed
33.3%
Median wait
8 weeks

Householder appeals to the Planning Inspectorate decided in the same 12 months. England: 34.4% allowed.

Local constraints

  • Bedford has published 29 conservation areas.
  • Bedford has not published Article 4 data to the national planning data platform.

Both can remove permitted development rights. Not every council has published its data yet, so check with the council before relying on permitted development.

Next steps for your extension